title: "The Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024"
id: 00393b30-291b-447e-b6b2-f3a2d4f19d33
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2024/955
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/00393b30-291b-447e-b6b2-f3a2d4f19d33
language: en
in_force_from: 2024-09-13
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2024/955/data.xml
read_on: 2026-11-10
sha256: b3f9888089e33120edc4c48b3730d615b2365d901556f683bd29fffa18ae0443
provisions: 4
---

# The Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024

## Title and introductory text {#prelims}

2024 No. 955
Infrastructure Planning
The Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024
Made
12th September 2024
Coming into force
13th September 2024
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for a non-material change to the Thurrock Flexible Generation Plant Development Consent Order 2022.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations , has decided to make the change on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:

## 1 Citation and commencement {#article-1}

This Order may be cited as the Thurrock Flexible Generation Plant Consent (Amendment No. 2) Order 2024 and comes into force on 13th September 2024.

## 2 Amendment to the Thurrock Flexible Generation Plant Development Consent Order 2022 {#article-2}

The Thurrock Flexible Generation Plant Development Consent Order 2022 (“the 2022 Order”) is amended in accordance with this Order.

## 3 Amendment to Schedule 1 (Authorised Development) {#article-3}

In Schedule 1 to the 2022 Order (Authorised Development), in the description of Work no. 1 in 1A replace at 1A(b) “up to 48 gas reciprocating engines” with “up to 96 gas reciprocating engines”.