title: "The Burbo Bank Extension Offshore Wind Farm (Correction) Order 2014"
id: 2c9427e6-61e8-49f0-9ed1-6b8bc0285c68
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2014/3301
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/2c9427e6-61e8-49f0-9ed1-6b8bc0285c68
language: en
in_force_from: 2014-12-11
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2014/3301/data.xml
read_on: 2026-11-10
sha256: 7a21d28027230992dbfef829c9ff5eca5ae943bdfaa4ee7ced00cfe1b94f6be8
provisions: 4
---

# The Burbo Bank Extension Offshore Wind Farm (Correction) Order 2014

## Title and introductory text {#prelims}

2014 No. 3301
Infrastructure Planning
The Burbo Bank Extension Offshore Wind Farm (Correction) Order 2014
Made
10th December 2014
Coming into force
11th December 2014
The Burbo Bank Extension Offshore Wind Farm Order 2014 (“the Order”), which granted development consent within the meaning of the Planning Act 2008 (“the Act”), contained correctable errors within the meaning of the Act.
Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request for the correction of errors in the Order.
There are no local planning authorities for the area in which the land to which the Order relates is situated that the Secretary of State is required to inform that the request has been received in accordance with paragraph 1(7) of Schedule 4 to the Act.
The Secretary of State, in exercise of the powers conferred by section 119 of, and Schedule 4 to, the Act, makes the following Order:

## 1 Citation and commencement {#article-1}

This Order may be cited as the Burbo Bank Extension Offshore Wind Farm (Correction) Order 2014 and comes into force on 11th December 2014.

## 2 Corrections {#article-2}

The Burbo Bank Extension Offshore Wind Farm Order 2014 is to be corrected as provided for in the table in the Schedule to this Order, where—
(a) the first column identifies the location of the correction;
(b) the second column quotes text to be omitted or otherwise identifies how a correction is to be made; and
(c) the third column identifies any text to be substituted or inserted.

## SCHEDULE {#schedule}

Article 2
Provision | Text to be omitted/how correction is to be made | Substituted or inserted text
Article 6(1)(b) | Insert after the second “agreed” | “; but paragraph (7) applies if the transferee or lessee is the holder of a licence under section 6 of the Electricity Act 1989”
Article 6(3)(b) | Insert after “agreed” | “; but paragraph (7) applies if the transferee or lessee is the holder of a licence under section 6 of the Electricity Act 1989”
Article 6 | Insert after paragraph (6) | “(7)Where the transferee or lessee under paragraph (1) or (3) is the holder of a licence under section 6 of the Electricity Act 1989—
(a) | the Secretary of State’s consent is not required for a transfer or grant;
(b) | the undertaker must notify the Secretary of State in writing before transferring or granting any benefit referred to in paragraph (1); and
(c) | the undertaker must notify MMO in writing before transferring or granting any deemed marine licence referred to in paragraph (3).”
Schedule 1, Part 3, paragraph 2 | Omit paragraph 2
Schedule 1, Part 3 | Insert a new heading before paragraph 3 | “Detailed design parameters”