---
title: "The Offshore Installations (Safety Zones) Order 2025"
id: 37b49c5a-ad4a-47f7-acdf-809841f73aa7
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2025/257
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/37b49c5a-ad4a-47f7-acdf-809841f73aa7
language: en
in_force_from: 2025-03-04
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2025/257/data.xml
read_on: 2026-11-10
sha256: 52ec5821e003382676b23dfbff6144d76281be019f8f7c5f0db5cbee31f5efb2
provisions: 4
---

# The Offshore Installations (Safety Zones) Order 2025

## Title and introductory text {#prelims}

2025 No. 257
OFFSHORE INSTALLATIONS
The Offshore Installations (Safety Zones) Order 2025
Made
4th March 2025
Coming into force in accordance with article 1(2)
The Secretary of State makes this Order—
in exercise of the powers conferred by section 22 of the Petroleum Act 1987; and
for the purpose of giving effect to proposals submitted by the Health and Safety Executive under section 24(2A) of that Act.

## 1 Citation and commencement {#article-1}

(1) This Order may be cited as the Offshore Installations (Safety Zones) Order 2025.
(2) This Order comes into force 21 days after the day on which it is made (“the general coming into force date”), except for article 2(2) which comes into force as provided in article 2(3).

## 2 Establishment of safety zones {#article-2}

(1) A safety zone is established around each installation specified in column 1 of the table in Part 1 of the Schedule (being an installation stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of 500 metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the table in Part 1 of the Schedule.
(2) A safety zone is established around each installation specified in column 1 of the table in Part 2 of the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of 500 metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 1984 specified in columns 2 and 3 of the table in Part 2 of the Schedule.
(3) Paragraph (2) comes into force, as respects each installation—
(a) on the general coming into force date, where the installation arrives at its station before that date; and
(b) when the installation arrives at its station, in any other case.

## Schedule Installations {#schedule}

Article 2
Part 1 Installations stationed at the time this Order is made
(1) Name or other designation | (2) Latitude | (3) Longitude
Teal West Development, Teal West Field, Block 21/24d | 57° 16.48’N | 0° 46.38’E
Victory PLEM (North), Victory Field, Block 207/1a | 60° 58.07’N | 01° 54.61’W
Victory PLEM (South), Victory Field, Block 207/1b | 60° 50.11’N | 01° 48.19’W
Part 2 Installations not stationed at the time this Order is made
(1) Name or other designation | (2) Latitude | (3) Longitude
Belinda Wellhead, Belinda Field, Block 21/30f | 57° 03.11’N | 0° 56.63’E
Gryphon Alpha, Gryphon Field, Block 9/18 | 59° 21.62’N | 01° 34.16’E
