title: "The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023"
id: 566667f7-45bf-4b93-8115-9455259efd24
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2023/1390
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/566667f7-45bf-4b93-8115-9455259efd24
language: en
in_force_from: 2023-12-14
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2023/1390/data.xml
read_on: 2026-11-10
sha256: 9c9a690e069c86b205a87f253c8047f7606f47b08781e5bb93629b5e5f6f635c
provisions: 4
---

# The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023

## Title and introductory text {#prelims}

2023 No. 1390
Infrastructure Planning
The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023
Made
13th December 2023
Coming into force
14th December 2023
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for a non-material change to the Norfolk Vanguard Offshore Wind Farm Order 2022.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations , has decided to make the change on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:

## 1 Citation and commencement {#article-1}

This Order may be cited as the Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023 and comes into force on 14th December 2023.

## 2 Amendment to The Norfolk Vanguard Offshore Wind Farm Order 2022 {#article-2}

The Norfolk Vanguard Offshore Wind Farm Order 2022 is amended in accordance with this Order.

## 3 Amendment to Part 3 (Requirements) of Schedule 1 (Authorised Project) {#article-3}

In Part 3 (Requirements) of Schedule 1 (Authorised Project), in paragraph 16(18), for “must not exceed two” substitute “must not exceed four”.