title: "The Electricity Act 1989 (Requirement of Consent for Solar Generating Stations) (England) Order 2025"
id: 6ec0c850-7972-463b-8075-c78c16cd223f
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2025/762
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/6ec0c850-7972-463b-8075-c78c16cd223f
language: en
in_force_from: 2025-12-31
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2025/762/data.xml
read_on: 2026-11-10
sha256: b84fddb84632d26eb058d562c4eb198d2fa915be1dd4efb7b343d0a200c35c59
provisions: 3
---

# The Electricity Act 1989 (Requirement of Consent for Solar Generating Stations) (England) Order 2025

## Title and introductory text {#prelims}

2025 No. 762
ELECTRICITY
The Electricity Act 1989 (Requirement of Consent for Solar Generating Stations) (England) Order 2025
Made
9th June 2025
Laid before Parliament
27th June 2025
Coming into force
31st December 2025
The Secretary of State makes this Order in exercise of the powers conferred by section 36(2) and (3) and section 111(2) of the Electricity Act 1989.

## 1 Citation, commencement and extent {#article-1}

(1) This Order may be cited as the Electricity Act 1989 (Requirement of Consent for Solar Generating Stations) (England) Order 2025 and comes into force on 31st December 2025.
(2) This Order extends to England and Wales.

## 2 Modification of section 36 of the Electricity Act 1989 {#article-2}

In the case of a generating station which generates electricity directly from sunlight and is situated in England, section 36(2)(a) of the Electricity Act 1989 has effect as if for “50 megawatts” there were substituted “100 megawatts”.