title: "The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024"
id: 8847cd85-9523-4cf5-ae24-e7ae3034b865
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2024/1151
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/8847cd85-9523-4cf5-ae24-e7ae3034b865
language: en
in_force_from: 2024-11-12
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2024/1151/data.xml
read_on: 2026-11-10
sha256: 601027facbf9d20ba4d62fdc85ff31b540b6aec37808580a39b026a7f5fff745
provisions: 4
---

# The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024

## Title and introductory text {#prelims}

2024 No. 1151
Infrastructure Planning
The Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024
Made
11th November 2024
Coming into force
12th November 2024
An application has been made to the Secretary of State under paragraph 2 of Schedule 6 to the Planning Act 2008, in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for a non-material change to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (“the 2015 Order”).
The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the 2011 Regulations, has decided to make this Order amending the 2015 Order.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order.

## 1 Citation and commencement {#article-1}

This Order may be cited as the Dogger Bank Teesside A and B Offshore Wind Farm (Amendment) Order 2024 and comes into force on 12thNovember 2024.

## 2 Amendment to the Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 {#article-2}

The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 is amended in accordance with this Order.

## 3 Amendment to Part 3 (requirements) of Schedule 1 (authorised project) {#article-3}

In Part 3 (requirements) of Schedule 1 (authorised project), in paragraph 5(8)(b) for “1,900 kilojoules” substitute “3,000 kilojoules”.