title: "The Hornsea Four Offshore Wind Farm (Amendment) Order 2024"
id: 9955c3a4-0064-4102-a36b-0421d6c8958d
authority: uk
place: "United Kingdom"
applies_also_from: []
kind: regulation
in_force: true
publisher_url: https://www.legislation.gov.uk/uksi/2024/800
attribution: "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
solon_url: https://solon.orangecat.ch/law/9955c3a4-0064-4102-a36b-0421d6c8958d
language: en
in_force_from: 2024-07-18
date_basis: publisher
status: consolidated
source_url: https://www.legislation.gov.uk/uksi/2024/800/data.xml
read_on: 2026-11-10
sha256: 6f6354d2cb52d34dd80fb2b8a7fb124c69a168269c16052e2b3b4a91cbdf1db0
provisions: 4
---

# The Hornsea Four Offshore Wind Farm (Amendment) Order 2024

## Title and introductory text {#prelims}

2024 No. 800
Infrastructure Planning
The Hornsea Four Offshore Wind Farm (Amendment) Order 2024
Made
17th July 2024
Coming into force
18th July 2024
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for non-material changes to the Hornsea Four Offshore Wind Farm Order 2023.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by Regulations 6 and 7 of the 2011 Regulations, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—

## 1 Citation and commencement {#article-1}

This Order may be cited as the Hornsea Four Offshore Wind Farm (Amendment) Order 2024 and comes into force on 18th July 2024.

## 2 Amendment to the Hornsea Four Offshore Wind Farm Order 2023 {#article-2}

The Hornsea Four Offshore Wind Farm Order 2023 (“the 2023 Order”) is amended in accordance with this Order.

## 3 Amendments to Schedule 16 of the 2023 Order {#article-3}

In Part 2 of Schedule 16 to the 2023 Order—
(a) in paragraph 3(d) for “four full kittiwake breeding seasons” substitute “two full kittiwake breeding seasons”; and
(b) in paragraph 4, for “four full breeding seasons” substitute “two full breeding seasons”.