Propose a change

The Dogger Bank Creyke Beck Offshore Wind Farm (Amendment) Order 2025

Write the words of this act the way you think they should read. Solon shows your change as a redline against the published text and pins it to that exact text, so it can never be applied to wording you did not see.

Change 1

What to do with it
As published

9 Amendment to Part 3 (Requirements) of Schedule 1 (Authorised Project)

Schedule 1 (Authorised Project), Part 3 (Requirements), paragraph 25 is amended as follows— (a) in paragraph 25(1)— (i) for “Work No. 7” substitute “the Project A converter station”; (ii) after “must”, delete “each or together”; (iii) after “35 decibels”, insert “(including when taken as a whole with the Project B converter station)”. (b) after paragraph 25(1) insert— (1A) The noise emanating from the operation of the Project B converter station (including transformers, cooling fans, switch gear and power lines) must not exceed operational noise levels of 35 decibels (including when taken as a whole with the Project A converter station) as given in BS4142 at the nearest receptors identified on the works plans as follows (with grid references shown as easting: northing)— (a) Halfway House (504796; 436331); (b) Model Farm (504011; 436576); (c) Poplar Farm (503727; 435672); and (d) Wanlass Farm (504385; 435168). ; (c) in paragraph 25(3), after “in relation to the”, insert “Project A”; (d) after paragraph 25(3) insert— (3A) All standby generator testing in relation to the Project B onshore works must be undertaken between 9 a.m. and 5 p.m. on Monday to Saturday, and not at all on Sundays or public or bank holidays, unless otherwise agreed in writing with the relevant planning authority. .

Your change, as a redline

9 Amendment to Part 3 (Requirements) of Schedule 1 (Authorised Project)

Schedule 1 (Authorised Project), Part 3 (Requirements), paragraph 25 is amended as follows— (a) in paragraph 25(1)— (i) for “Work No. 7” substitute “the Project A converter station”; (ii) after “must”, delete “each or together”; (iii) after “35 decibels”, insert “(including when taken as a whole with the Project B converter station)”. (b) after paragraph 25(1) insert— (1A) The noise emanating from the operation of the Project B converter station (including transformers, cooling fans, switch gear and power lines) must not exceed operational noise levels of 35 decibels (including when taken as a whole with the Project A converter station) as given in BS4142 at the nearest receptors identified on the works plans as follows (with grid references shown as easting: northing)— (a) Halfway House (504796; 436331); (b) Model Farm (504011; 436576); (c) Poplar Farm (503727; 435672); and (d) Wanlass Farm (504385; 435168). ; (c) in paragraph 25(3), after “in relation to the”, insert “Project A”; (d) after paragraph 25(3) insert— (3A) All standby generator testing in relation to the Project B onshore works must be undertaken between 9 a.m. and 5 p.m. on Monday to Saturday, and not at all on Sundays or public or bank holidays, unless otherwise agreed in writing with the relevant planning authority. .

One line that says what changes, such as "Halve the dog tax".

Who it helps, what it costs, what it fixes. It is what persuades people to support it.

A proposal here is not law. Support on Solon is evidence that people want the change; the official route says what it takes to make it law.

Sign in to file your proposal. What you have written stays on this page.

Sign in to file it

Think it through

Ask what your change would do, who would gain and who would bear a cost, and where something like it is already law. The assistant reads your draft as it stands, cites the law and the studies it finds, and takes no side. What you file stays yours.

Questions to start with
Think it through
Legal information from the published text, not advice for your case. Check the sources. Find a law · What the register holds