1 Citation and commencement
This Order may be cited as the Cottam Solar Project (Correction) Order 2024 and comes into force on 26th November 2024.
Propose a change2 Corrections
The Cottam Solar Project Order 2024 is corrected as set out in the table in the Schedule (corrections) to this Order, in which—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text which is to be substituted, inserted or omitted.
Propose a changeSCHEDULE CORRECTIONS
Article 2
Column (1) Where the correction is made | Column (2) How the correction is made | Column (3) Text substituted, inserted or omitted
Part 1, Interpretation, Article 2 – definition of “Gate Burton Energy Park Order” | For “the Gate Burton Energy Park Order means ”the Gate Burton Energy Park Order 2024(b)” substitute | “the Gate Burton Energy Park Order” means the Gate Burton Energy Park Order 2024(b)”
Part 1, Interpretation, Article 2 – definition of “West Burton Solar Project Order” | Before “granted” insert | “is”
Article 14(1)(c) | For “article 10(1)” substitute | “article 10”
Article 16(7) | After “Water Resources” insert | “Act”
Article 23(1) | After “1965 Act” insert | “,whichever is earliest”
Article 35(6) | For “fourteen” substitute | “ten”
Article 45(2) | For “may” substitute | “must”
Schedule 1 shoulder note | Omit | “Article 1 and”
Schedule 1, Authorised Development, Work No. 3(a) | For “fsprinkler” substitute | “sprinkler”
Schedule 2, paragraph 1 – definition of “relevant planning authority” | For “(c) Northamptonshire Country Council” substitute | “(c) Nottinghamshire County Council”
After “(d) Lincolnshire County Council, ” omit | “, West Lindsay District Council and Bassetlaw District Council”
Schedule 2, paragraph 8(3) | For “plan” substitute | “strategy”
Schedule 13, Part 1, Documents and Plans, row 2 (“Book of reference”), column (3) (“Revision number”) | For “G” substitute | “F”
Schedule 13, Part 1, Documents and Plans, row 10 (“Outline Construction Traffic Management Plan”), column (2) (“Document Reference”) | For “EN010132/APP/C6.3” substitute | “EN010133/APP/C6.3”
Schedule 13, Part 1, Documents and Plans, row 10 (“Outline Construction Traffic Management Plan”), column (3) (“Revision number”) | For “F” substitute | “G”
Schedule 13, Part 1, Documents and Plans, row 10 (“Outline Construction Traffic Management Plan”), column (4) (“Date”) | For “February” substitute | “August”
Schedule 13, Part 1, Documents and Plans, row 11 (“Outline decommissioning Statement”), column (3) (“Revision number”) | For “A” substitute | “B”
Schedule 13, Part 1, Documents and Plans, row 11 (“Outline decommissioning Statement”), column (4) (“Date”) | For “December 2023” substitute | “August 2024”
Schedule 13, Part 1, Documents and Plans, row 14 (“Outline landscape and ecological management plan”), column (3) (“Revision number”) | For “E” substitute | “F”
Schedule 13, Part 1, Documents and Plans, row 14 (“Outline landscape and ecological management plan”), column (4) (“Date”) | For “January” substitute | “August”
Schedule 13, Part 1, Documents and Plans, row 15 (“Outline operational environmental management plan”), column (3) (“Revision number”) | For “D” substitute | “E”
Schedule 13, Part 1, Documents and Plans, row 15 (“Outline operational environmental management plan”), column (4) (“Date”) | For “February” substitute | “August”
Schedule 13, Part 1, Documents and Plans, row 18 (“Outline soil management plan”) column (2) (“Document reference”) | For “EN010133/APP/C7. 18” substitute | “EN010133/APP/C6.3.19.2”
Schedule 13, Part 1, Documents and Plans, row 20 (“Streets plan”) column (2) (“Document reference”) | For “EN010133/APP/C2.1 3_A” substitute | “EN010133/APP/C2.13”
Schedule 13, Part 1, Documents and Plans, row 21 (“Works plan”) column (3) (“Revision number”) | For “C” substitute | “D”
Schedule 13, Part 1, Documents and Plans, row 21 (“Works plan”) column (4) (“Date”) | For “January” substitute | “August”
Schedule 13, Part 1, Documents and Plans, row 22 (“Written Scheme of Investigation”) column (2) (“Document reference”) | For “EN010133/APP/C8.2. 14” substitute | “EN010133/EX5/C8.2.14”
Schedule 13, Part 2, Substitute and Supplementary Documents, row 3 (“Environmental Statement, Chapter 8: Landscape and Visual Impact”) column (5) (“Examination library reference”) | For “[REP-012]” substitute | “[REP2-008]”
Schedule 13, Part 2, Substitute and Supplementary Documents, row 6 (“Environmental Statement, Without Prejudice Archaeological WSI”) | Omit | Row 6
Schedule 15, Part 3, paragraph 28(7) | For “(7) Not” substitute | “(7) The undertaker is not”
Schedule 15, Part 3, paragraph 30(2) | After “taking of action by the undertaker, it”, delete “may” and substitute | “must”
Schedule 15, Part 8, paragraph 93 | At the end of the definition of “construction” for “.” substitute | “;”
At the end of the definition of “evidence” omit | “and”
At the end of the definition of “plans” after “statements;” insert | “and”
Schedule 15, Part 8, paragraph 94(3)(a) | For “may” substitute | “must”
Schedule 15, Part 10, paragraph 119(2) | After “under sub-paragraph (1)”, delete “may” and substitute | “must”
Schedule 15, Part 10, paragraph 125(5) | After “Network Rail’s apparatus, Network Rail” delete “may” and substitute | “must”
Schedule 15, Part 11, paragraph 141 | After “consent of Gate Burton, which” delete “may” and substitute | “must”
Schedule 15, Part 11, paragraph 142(1) | After “consent of Gate Burton, which” delete “may” and substitute | “must”
Schedule 15, Part 12, paragraph 157 | After “consent of West Burton, which” delete “may” and substitute | “must”
Schedule 15, Part 12, paragraph 158(1) | After “consent of West Burton, which” delete “may” and substitute | “must”
Schedule 15, Part 13, paragraph 170(6) | After “sub-paragraphs (1) to (5)” delete “may” and substitute | “must”
Schedule 15, Part 15, paragraph 210(3) | After “required by this Part of this Schedule it” delete “may” and substitute | “must”
Schedule 15, Part 17, paragraph 223 | After “consent of Tillbridge, which” delete “may” and substitute | “must”
Schedule 15, Part 17, paragraph 224(1) | After “consent of Tillbridge, which” delete “may” and substitute | “must”
Schedule 15, Part 18, paragraph 243(4)(b) | For “may” substitute | “must”
Schedule 15, Part 18, paragraph 247(2) | After “by the undertaker, it” delete “may” and substitute | “must”
Schedule 15, Part 19, paragraph 253(4) | After “sub-paragraph (3)” delete “may” and substitute | “must”