The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014

Write the words of this act the way you think they should read. Solon shows your change as a redline against the published text and pins it to that exact text, so it can never be applied to wording you did not see.

Change 1

What to do with it
As published

SCHEDULE 11 PROTECTIVE WORKS

Article 20 Part of Work No. 5(c)— works to protect the existing river wall. Work No. 5(d)— works to strengthen or support the existing river wall landward of the Putney Embankment Foreshore temporary slipway. Work No. 6(b)(iii)— strengthening and alteration of existing river wall to the south of Whiffin Wharf, and strengthening or replacing the existing river wall to the south of Hurlingham Wharf and Carnwath Road Industrial Estate. Work No. 8(b)(ii)— strengthening and alteration of the existing river wall to the south of Bell Lane Creek and works to protect and or strengthen the river wall on the north side of Bell Lane Creek. Work No. 11(c)(iii)— replacement or other works to protect or strengthen the existing flood defence on the western boundary of the site. Part of Work No. 12(c)— works to protect the existing river wall. Part of Work No. 13(b)(iii)— works to protect or strengthen the existing river wall. Part of Work No. 14(c)(ii)— works to protect or strengthen the existing river wall to east and west of Work No. 14(c)(i) and the existing Middle Wharf jetty. Work No. 15(c)(ii)— works to protect and strengthen the existing slipway and existing river wall. Part of Work No. 16(c)— works to protect the existing river wall and adjoining structures. Part of Work No. 17(b)— works to protect the existing river wall and adjoining structures. Part of Work No. 18— works to replace or protect the boundary wall on the west side of the existing facilities building. Part of Work No. 19(b)— works to protect or strengthen the river wall and adjoining structures at the western end of the site. Part of Work No. 19(b)(i)— works to replace, protect or strengthen the existing river wall to the west of Fountain Green Square. Part of Work No. 23(b)— works to protect or strengthen the existing Docklands Light Railway viaduct. Part of Work No. 23(b)(i)— works to protect or strengthen the existing river wall. Part of Work No. 24(b)— works to protect or strengthen the existing river wall. Work No. 24(b)(v)— works to protect or strengthen the existing river wall.

Your change, as a redline

SCHEDULE 11 PROTECTIVE WORKS

Article 20 Part of Work No. 5(c)— works to protect the existing river wall. Work No. 5(d)— works to strengthen or support the existing river wall landward of the Putney Embankment Foreshore temporary slipway. Work No. 6(b)(iii)— strengthening and alteration of existing river wall to the south of Whiffin Wharf, and strengthening or replacing the existing river wall to the south of Hurlingham Wharf and Carnwath Road Industrial Estate. Work No. 8(b)(ii)— strengthening and alteration of the existing river wall to the south of Bell Lane Creek and works to protect and or strengthen the river wall on the north side of Bell Lane Creek. Work No. 11(c)(iii)— replacement or other works to protect or strengthen the existing flood defence on the western boundary of the site. Part of Work No. 12(c)— works to protect the existing river wall. Part of Work No. 13(b)(iii)— works to protect or strengthen the existing river wall. Part of Work No. 14(c)(ii)— works to protect or strengthen the existing river wall to east and west of Work No. 14(c)(i) and the existing Middle Wharf jetty. Work No. 15(c)(ii)— works to protect and strengthen the existing slipway and existing river wall. Part of Work No. 16(c)— works to protect the existing river wall and adjoining structures. Part of Work No. 17(b)— works to protect the existing river wall and adjoining structures. Part of Work No. 18— works to replace or protect the boundary wall on the west side of the existing facilities building. Part of Work No. 19(b)— works to protect or strengthen the river wall and adjoining structures at the western end of the site. Part of Work No. 19(b)(i)— works to replace, protect or strengthen the existing river wall to the west of Fountain Green Square. Part of Work No. 23(b)— works to protect or strengthen the existing Docklands Light Railway viaduct. Part of Work No. 23(b)(i)— works to protect or strengthen the existing river wall. Part of Work No. 24(b)— works to protect or strengthen the existing river wall. Work No. 24(b)(v)— works to protect or strengthen the existing river wall.

One line that says what changes, such as "Halve the dog tax".

Who it helps, what it costs, what it fixes. It is what persuades people to support it.

How this law is officially changed

Solon does not know this law's official route yet. The proposal is recorded all the same, and the route appears here once its source is added.

A proposal here is not law. Support on Solon is evidence that people want the change; the official route says what it takes to make it law.

Sign in to file your proposal. What you have written stays on this page.

Sign in to file it

Think it through

Ask what your change would do, who would gain and who would bear a cost, and where something like it is already law. The assistant reads your draft as it stands, cites the law and the studies it finds, and takes no side. What you file stays yours.

Questions to start with
Think it through
Legal information from the published text, not advice for your case. Check the sources. Find a law · What the register holds