Propose a change

Planning (Listed Buildings and Conservation Areas) Act 1990

Write the words of this act the way you think they should read. Solon shows your change as a redline against the published text and pins it to that exact text, so it can never be applied to wording you did not see.

Change 1

What to do with it
As published

18 Limit of duration of listed building consent.

(1) Subject to the provisions of this section, every listed building consent shall be granted subject to the condition that the works to which it relates must be begun not later than the expiration of— (a) three years beginning with the date on which the consent is granted; or (b) such other period (whether longer or shorter) beginning with that date as the authority granting the consent may direct, being a period which the authority considers appropriate having regard to any material considerations. (2) If listed building consent is granted without the condition required by subsection (1), it shall be deemed to have been granted subject to the condition that the works to which it relates must be begun not later than the expiration of three years beginning with the date of the grant. (2A) In subsections (2A) to (2BB)— “implementation period” means the period before the end of which works to which a listed building consent relates are required to be begun in pursuance of subsection (1) or (2); “relevant proceedings” means proceedings to challenge the validity of a grant of listed building consent or of a deemed grant of listed building consent. (2B) If a person is given permission by a court to bring relevant proceedings, the implementation period is extended by one year. (2BA) If a party to relevant proceedings is given permission to appeal to the Court of Appeal against a decision determining the challenge, the implementation period is extended by one year. (2BB) If a party to relevant proceedings is given permission to appeal to the Supreme Court against a decision determining the challenge, the implementation period is extended by two years. (2BC) Any extension of a period under subsection (2B), (2BA) or (2BB) is to run concurrently with any other extension of the period under the same subsection (so far as they overlap). (2BD) Any extension of a period under subsection (2BA) is to run consecutively to the previous extension of the period under subsection (2B) (if they would otherwise overlap). (2BE) Any extension of a period under subsection (2BB) is to run consecutively to the previous extension of the period under subsection (2B) and any previous extension of the period under subsection (2BA) (if they would otherwise overlap). (2BF) The references in subsections (2BA) and (2BB) to determining a challenge are to determining it after a full hearing (and accordingly do not include a refusal of permission or leave). (2C) Nothing in this section prevents the works being begun from the time the consent is granted. (3) Nothing in this section applies to any consent to the retention of works granted under section 8(3).

Your change, as a redline

18 Limit of duration of listed building consent.

(1) Subject to the provisions of this section, every listed building consent shall be granted subject to the condition that the works to which it relates must be begun not later than the expiration of— (a) three years beginning with the date on which the consent is granted; or (b) such other period (whether longer or shorter) beginning with that date as the authority granting the consent may direct, being a period which the authority considers appropriate having regard to any material considerations. (2) If listed building consent is granted without the condition required by subsection (1), it shall be deemed to have been granted subject to the condition that the works to which it relates must be begun not later than the expiration of three years beginning with the date of the grant. (2A) In subsections (2A) to (2BB)— “implementation period” means the period before the end of which works to which a listed building consent relates are required to be begun in pursuance of subsection (1) or (2); “relevant proceedings” means proceedings to challenge the validity of a grant of listed building consent or of a deemed grant of listed building consent. (2B) If a person is given permission by a court to bring relevant proceedings, the implementation period is extended by one year. (2BA) If a party to relevant proceedings is given permission to appeal to the Court of Appeal against a decision determining the challenge, the implementation period is extended by one year. (2BB) If a party to relevant proceedings is given permission to appeal to the Supreme Court against a decision determining the challenge, the implementation period is extended by two years. (2BC) Any extension of a period under subsection (2B), (2BA) or (2BB) is to run concurrently with any other extension of the period under the same subsection (so far as they overlap). (2BD) Any extension of a period under subsection (2BA) is to run consecutively to the previous extension of the period under subsection (2B) (if they would otherwise overlap). (2BE) Any extension of a period under subsection (2BB) is to run consecutively to the previous extension of the period under subsection (2B) and any previous extension of the period under subsection (2BA) (if they would otherwise overlap). (2BF) The references in subsections (2BA) and (2BB) to determining a challenge are to determining it after a full hearing (and accordingly do not include a refusal of permission or leave). (2C) Nothing in this section prevents the works being begun from the time the consent is granted. (3) Nothing in this section applies to any consent to the retention of works granted under section 8(3).

One line that says what changes, such as "Halve the dog tax".

Who it helps, what it costs, what it fixes. It is what persuades people to support it.

A proposal here is not law. Support on Solon is evidence that people want the change; the official route says what it takes to make it law.

Sign in to file your proposal. What you have written stays on this page.

Sign in to file it

Think it through

Ask what your change would do, who would gain and who would bear a cost, and where something like it is already law. The assistant reads your draft as it stands, cites the law and the studies it finds, and takes no side. What you file stays yours.

Questions to start with
Think it through
Legal information from the published text, not advice for your case. Check the sources. Find a law · What the register holds