Law

The Sunnica Energy Farm (Correction) Order 2024

United Kingdom · regulation

Ask the law about thisMore laws of United KingdomFor machines: Markdown

Open at the publisher →

In force since 2024-11-13, as the publisher states.

Copy read on 2026-11-10. The page it was read from

Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

sha256 50c1078f1a3cc8168672f9c096cfaa89f3d1a8ff1aafafc7f8ed0a083bf4dd5f

Contents: 4 provisions
  1. Title and introductory text
  2. 1 Citation and commencement
  3. 2 Corrections
  4. SCHEDULE Corrections

Proposed changes to this act

No one has proposed a change to this act yet.

How this law is officially changed

Solon does not know this law's official route yet. The proposal is recorded all the same, and the route appears here once its source is added.

4 provisions

Title and introductory text

2024 No. 1154 Infrastructure Planning The Sunnica Energy Farm (Correction) Order 2024 Made 12th November 2024 Coming into force 13th November 2024 The Sunnica Energy Farm Order 2024 (“the Order”), which granted development consent within the meaning of the Planning Act 2008 (“the Act”), contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act. In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicant for the correction of errors in the Order. In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed East Cambridgeshire District Council and West Suffolk Council as the relevant local planning authorities, that the request has been received. The Secretary of State, in exercise of the powers conferred by paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order—

Propose a change

1 Citation and commencement

This Order may be cited as the Sunnica Energy Farm (Correction) Order 2024 and comes into force on 13thNovember 2024.

Propose a change

2 Corrections

The Sunnica Energy Farm Order 2024 is corrected as set out in the table in the Schedule to the Order, in which— (a) column 1 sets out where the correction is to be made; (b) column 2 sets out how the correction is to be made; and (c) column 3 sets out the text which is to be substituted, inserted or omitted.

Propose a change

SCHEDULE Corrections

Article 2 Column (1) Where the correction is made | Column (2) How the correction is made | Column (3) Text substituted, inserted or omitted Article 35(2)(d) | After “breach”, omit | “of” Schedule 2, Requirement 6(1)(k) | For “/” substitute | “or” Schedule 2, Requirement 6(1)(k) | For “Construction and Traffic Management Plan,” substitute | “framework construction traffic management plan and travel plan,” Schedule 8, row: 1-02 | Omit | Row 1-02 Schedule 8, row: 1-03 | Omit | Row 1-03 Schedule 8, row: 5-11 | Omit | Row 5-11 Schedule 8, row: 16-14, column (2) | Omit | “and access rights” Schedule 8, row: 16-15, column (2) | After “Cable rights”, insert | “and access rights” Schedule 10, row: land and Crown land plans, column (3) | For “7”, substitute | “6” Schedule 10, row: land and Crown land plans, column (4) | For “30/08/2023”, substitute | “30/01/2023” Schedule 12, paragraph 14(4) | For “39”, substitute | “38” Schedule 12, paragraph 99(2) | For “(cable works beneath the width of the highway)”, substitute | “(streets subject to street works)”