Law

The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Moray East) (Scotland) Order 2023

United Kingdom · regulation

Ask the law about thisMore laws of United KingdomFor machines: Markdown

Open at the publisher →

In force since 2023-10-09, as the publisher states.

Copy read on 2026-11-10. The page it was read from

Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

sha256 58471925d7c5053cefe6c1de969df692080c05da4ca8f6ea6879a4685717bd8c

Contents: 3 provisions
  1. Title and introductory text
  2. 1 Citation, commencement, extent and application
  3. 2 Exemption from section 4(1)(b) of the Electricity Act 1989

Proposed changes to this act

No one has proposed a change to this act yet.

How this law is officially changed

Solon does not know this law's official route yet. The proposal is recorded all the same, and the route appears here once its source is added.

3 provisions

Title and introductory text

2023 No. 981 Electricity, Scotland The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Moray East) (Scotland) Order 2023 Made 7th September 2023 Laid before Parliament 11th September 2023 Coming into force 9th October 2023 The Secretary of State makes this Order in exercise of the powers conferred by section 5(1) of the Electricity Act 1989. The Secretary of State has given notice of the proposal to make this Order in accordance with section 5(2) and (3) of that Act and has consulted with the Scottish Ministers, and has considered any representations made.

Propose a change

1 Citation, commencement, extent and application

(1) This Order may be cited as the Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Moray East) (Scotland) Order 2023 and comes into force on 9thOctober 2023. (2) This Order extends to England and Wales and Scotland. (3) This Order applies in relation to Scotland only.

Propose a change

2 Exemption from section 4(1)(b) of the Electricity Act 1989

(1) The Secretary of State grants exemption from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply) to Moray Offshore Windfarm (East) Limited in respect of transmission taking place over the transmission system connected to the Moray East Offshore Wind Farm. (2) The exemption in paragraph (1) of this article applies for the period beginning with 9thOctober 2023 and ending with the earlier of— (a) the day after the day on which the transmission system connected to Moray East Offshore Wind Farm is transferred to a successful bidder; (b) 31st March 2024. (3) In this article— (a) “the Act” means the Electricity Act 1989; (b) Moray East Offshore Wind Farm means the generating station located in the Moray Firth, in the Northeast of Scotland with its central point being approximately Latitude 58°10′01″ and Longitude 2°41′55″; (c) Moray Offshore Windfarm (East) Limited means Moray Offshore Windfarm (East) Limited, a company registered in England and Wales with company number 07101438; (d) “successful bidder” means, in relation to the transfer of a transmission system, a person to whom, as a result of a tender exercise, an offshore transmission licence within the meaning of section 6C(5) of the Act (competitive tenders for offshore transmission licences) has been or is to be granted in respect of that transmission system.

Propose a change