Law

The Feed-in Tariffs (Amendment) Order 2014

United Kingdom · regulation

Ask the law about thisMore laws of United KingdomFor machines: Markdown

Open at the publisher →

In force since 2014-07-14, as the publisher states.

Copy read on 2026-11-10. The page it was read from

Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

sha256 9e05faf1a026a30ace2a4b90afa290f7c4e44b6728090fad6fdef2d5ecd9ed8c

Contents: 3 provisions
  1. Title and introductory text
  2. 1 Citation and commencement
  3. 2 Amendment to the Feed-in Tariffs Order 2012

Proposed changes to this act

No one has proposed a change to this act yet.

How this law is officially changed

Solon does not know this law's official route yet. The proposal is recorded all the same, and the route appears here once its source is added.

3 provisions

Title and introductory text

2014 No. 1601 Electricity The Feed-in Tariffs (Amendment) Order 2014 Made 11th June 2014 Laid before Parliament 20th June 2014 Coming into force 14th July 2014 The Secretary of State, in exercise of the powers conferred by sections 43(3)(a) and 104(2) of the Energy Act 2008, makes the following Order:

Propose a change

1 Citation and commencement

This Order may be cited as the Feed-in Tariffs (Amendment) Order 2014 and comes into force on 14th July 2014.

Propose a change

2 Amendment to the Feed-in Tariffs Order 2012

After article 17 of the Feed-in Tariffs Order 2012, insert— Withdrawal of preliminary accreditation for certain hydro generating stations 17A. (1) The Authority must withdraw any preliminary accreditation granted under article 9 in respect of a relevant hydro generating station if— (a) it is requested to do so by notice from the prospective FIT generator in respect of that relevant hydro generating station; and (b) it is satisfied that the application for preliminary accreditation in respect of the relevant hydro generating station was received by the Authority during the period beginning with 1st December 2012 and ending with 31st December 2012. (2) Where the Authority withdraws a preliminary accreditation in accordance with paragraph (1) it must give notice to the prospective FIT generator specifying the date on which the withdrawal has effect. (3) In this article— “prospective FIT generator” has the same meaning as in article 9; and “relevant hydro generating station” means a hydro generating station with a total installed capacity greater than 100kW but not exceeding 500kW.