1 Citation and commencement
This Order may be cited as the Net Zero Teesside (Correction) Order 2024 and comes into force on 21st December 2024.
Propose a change2 Corrections
The 2024 Order is corrected as set out in the table in the Schedule to this Order, where—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text to be substituted, inserted or omitted.
Propose a changeSCHEDULE
Article 2
(1) Where the correction is to be made | (2) How the correction is to be made | (3) Text to be substituted, inserted or omitted (if any)
Article 2 (interpretation) – definition of “the 1966 Act” | For “Hartlepool” substitute | “Hartlepools”
Article 2 (interpretation) – definition of “commence” sub-paragraph (b) | Omit “which explains” | “which explains”
Article 2 (interpretation) – definition of “undertaker” sub-paragraph (a) | After “NZT Power;” insert | “and”
Article 2 (interpretation) – definition of “working day” | After “Banking and Financial Dealings Act 1971(30);” insert | “and”
Article 3(1)(a) (electronic communications) | After “in electronic form;” insert | “and”
Article 8(8) (consent to transfer benefit of this Order) | Substitute “paragraph 8(7)” with | “paragraph (7)”
Article 8(9)(d) (consent to transfer benefit of this Order) | Omit “pursuant to paragraph (4)” | “pursuant to paragraph (4)”
Article 21(5) (removal of human remains) | Omit “and that person must, as soon as reasonably practicable after such re-interment or cremation, provide to the undertaker a certificate for the purpose of enabling compliance with paragraph (10) ” | “and that person must, as soon as reasonably practicable after such re-interment or cremation, provide to the undertaker a certificate for the purpose of enabling compliance with paragraph (10) ”
Article 27(9) (application of the 1981 Act) | After “But see article 28 (acquisition of subsoil or airspace only)” insert | “of the Net Zero Teesside Order 2024”
Article 29(2) (modification of Part 1 of the 1965 Act) | After “article 24 (time limit for exercise of authority to acquire land compulsorily)” insert | “of the Net Zero Teesside Order 2024”
Article 31(3)(a) (temporary use of land for carrying out the authorised development) | After “on which the notice is given;” insert | “and”
Schedule 1 (authorised development)
Schedule 1 | After Stockton replace “and” with “on” | “on”
Schedule 8 (modification of compensation and compulsory purchase enactments for creation of new rights and imposition of new restrictive covenants)
Paragraph 3(2)(a) | After “Net Zero Teesside Order 2024” insert | “)”
Paragraph 3(2)(b) | After “Net Zero Teesside Order 2024” insert | “)”
Paragraph 5(5) | After “(compulsory acquisition of land)” insert | “)”
Schedule 12 (protective provisions)
Part 3 (for the protection of National Grid Electricity Transmission as electricity undertaker), paragraph 18 – definition of “specified works” | Before “activity” insert | “is an ”
Part 3, paragraph 25(1)(e) | After “protective works;” insert | “and”
Part 4 (for the protection of National Gas Transmission PLC as gas undertaker), paragraph 38(2) | Substitute “subparagraph” with “sub-paragraph” | “sub-paragraph”
Part 6 (for the protection of CATS North Sea Limited), definition of “CATS” | Insert comma and space after “1” | “, ”
Part 6 (for the protection of CATS North Sea Limited), paragraph 59 – definition of “CATS pipeline(s)”, sub-paragraph (d) | After “storage site;” insert | “and”
Part 6, paragraph 69(3) | Substitute “paragraph (2)” with | “sub-paragraph (2)”
Part 7 (for the protection of CF Fertilisers UK Limited), paragraph 84(2)(a)(v) | After “CF Fertilisers;” insert | “and”
Part 11 (for the protection of railway interests), paragraph 112(1) – definition of “regulatory consents” | After “authorised development;” omit | “and”
Part 11, paragraph 112(1) – definition of “specified work” | Substitute “.” with | “; and”
Part 11, paragraph 121(8)(a) | After “apparatus;” insert | “and”
Part 11, paragraph 125(1)(e) | After “development” insert | “,”
Part 11, paragraph 130 | Substitute “(consent to transfer of benefit or Order) of this Order)” with | “(consent to transfer benefit of this Order)”
Part 12 (for the protection of Northern Powergrid (Northeast) PLC), paragraph 143 | Substitute “in this Part of the Schedule” with | “in this Part of this Schedule”
Part 12 (for the protection of Northern Powergrid (Northeast) PLC), paragraph 143 | Substitute “under this Part of the Schedule” with | “under this Part of this Schedule”
Part 12, paragraph 149 | Substitute “this Part of the Schedule” with | “this Part of this Schedule”
Part 15 (for the protection of Redcar Bulk Terminal Limited), paragraph 185(3) | Substitute “subparagraph” with | “sub-paragraphs”
Part 16 (for the protection of Sabic Petrochemicals UK Limited), paragraph 188 – definition of “SABIC” | Substitute “SABIC Petrochemicals UK Limited” with | “SABIC UK Petrochemicals Limited”
Part 16 (for the protection of Sabic Petrochemicals UK Limited), paragraph 188 – definition of “specified persons” | Substitute “, SABIC Petrochemicals UK Limited” with | “, SABIC UK Petrochemicals Limited”
Part 16 (for the protection of Sabic Petrochemicals UK Limited), paragraph 188 – definition of “specified persons” | Substitute “to SABIC Petrochemicals UK Limited” with | “to SABIC UK Petrochemicals Limited”
Part 16 (for the protection of Sabic Petrochemicals UK Limited), paragraph 189(1)(b) | Substitute “sub-paragraph 188(3) below” with | “paragraph 189(3) below”
Part 16 (for the protection of Sabic Petrochemicals UK Limited), paragraph 192(2) | Substitute “paragraph 191(1)” with | “paragraph 192(1)”
Part 16 (for the protection of Sabic Petrochemicals UK Limited), paragraph 193(1)(b) | Substitute “.” with | “,”
Part 17 (for the protection of the Sembcorp Protection Corridor), paragraph 213(2) | Substitute “(consent to transfer benefit of Order)” to | “(consent to transfer benefit of this Order)”
Part 18 (for the protection of Anglo-American), paragraph 230 - definition of “Woodsmith Project” | Substitute “Agreement” with | “Order”
Part 18 (for the protection of Anglo-American), paragraph 232(a)(ii) | After “its” delete | “contractors,”
Part 18 (for the protection of Anglo-American), paragraph 237(a) | Substitute “BH0627,” with | “BH0627 and”
Part 18 (for the protection of Anglo-American), paragraph 240(4)(c) | After “of” omit | “the”
Part 18 (for the protection of Anglo-American), paragraph 240(4)(c) | Substitute “on” with | “or”
Part 20 (for the protection of South Tees Development Corporation), paragraph 258 – definition of “red main criteria” paragraph (a) | After “route” insert | “that”
,Part 20 (for the protection of South Tees Development Corporation), paragraph 261 | Substitute “58” with | “260”
Part 20 (for the protection of South Tees Development Corporation), paragraph 285(2) | After “261” omit | “A”
Part 23 (for the protection of Huntsman Polyurethanes (UK) Limited), paragraph 311(2) | Substitute “paragraph (1)” with | “sub-paragraph (1)“
Part 23 (for the protection of Huntsman Polyurethanes (UK) Limited), paragraph 312(3) | Substitute “paragraph (2)” with | “sub-paragraph (2)“
Part 23 (for the protection of Huntsman Polyurethanes (UK) Limited), paragraph 312(3) | Substitute “sub-paragraph (a) and (b) of paragraph 310(1)” with | “sub-paragraphs (a) and (b) of paragraph 311(1)”
Part 24 (for the protection of Navigator Terminals Seal Sands Limited), paragraph 337(2) | Substitute “with paragraph 336” | “with paragraph 339”
Part 24 (for the protection of Navigator Terminals Seal Sands Limited), paragraph 337(2) | Substitute “under paragraph 336” with | “under paragraph 339”
Part 26 (for the protection of Northern Gas Networks Limited), paragraph 359(4) | Omit “undertaker” | “undertaker”
Part 26 (for the protection of Northern Gas Networks Limited), paragraph 360(1)(a) | Before “357(4)” insert | “paragraph ”
Part 26 (for the protection of Northern Gas Networks Limited), paragraph 361(4)(b) | After “Undertaker” insert | “.”
Part 26 (for the protection of Northern Gas Networks Limited), paragraph 366 | Before “Schedule” insert | “Part of this”
Part 28 (for the protection of Teesside Gas & Liquids Processing, Teesside Gas Processing Plant Limited & Northern Gas Processing Limited), paragraph 377 | Substitute “386387” with | “389”
Part 28 (for the protection of Teesside Gas & Liquids Processing, Teesside Gas Processing Plant Limited & Northern Gas Processing Limited), paragraph 390 | After “in accordance” omit “with” | “with”
Schedule 14 (documents and plans to be certified)
Table 13, application guide, column (3) Revision number | Substitute “17” with “19” | “19”
Table 13, application guide, column (4) Date | Substitute “April” with “August” | “August”
Table 13, framework construction environmental management plan, column (2) Document reference | After “4” insert “.” | “.”
Table 13, indicative lighting strategy, column (3) Revision number | Substitute “1” with “2” | “2”
Table 13, indicative lighting strategy, column (4) Date | Substitute “May” with “October” | “October”
Table 13, parking plan, column (4) Date | Substitute “October” with “November” | “November”
Table 13, Sembcorp Pipeline Corridor protective provisions supporting plan, column (4) Date | Substitute “October” with “November” | “November”
Table 13, updated landscape and biodiversity plan, column (1) Document name | Substitute “updated” with “Indicative” | “Indicative”
Table 13, updated landscape and biodiversity plan, column (4) Date | Substitute “October” with “November” | “November”
Propose a change