Law

The Planning Act 2008 (Commencement No. 8) and Levelling-up and Regeneration Act 2023 (Commencement No. 4 and Transitional Provisions) Regulations 2024

United Kingdom · regulation

Ask the law about thisMore laws of United KingdomFor machines: Markdown

Open at the publisher →

In force since 2024-04-02, as the publisher states.

Copy read on 2026-11-10. The page it was read from

Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

sha256 9f7939b92cd86e6cc470da06bb167e60bbf831596d899bafa57460af58fa8e5a

Contents: 10 provisions
  1. Title and introductory text
  2. 1 Citation and interpretation
  3. 2 Provisions of the 2008 Act coming into force on 25th April 2024
  4. 3 Provisions of the 2023 Act coming into force on 25th April 2024
  5. 4 Provision of the 2023 Act coming into force on 25th July 2024
  6. 5 Transitional provision: time limits for enforcement
  7. 6 Transitional provision: duration of temporary stop notices
  8. 7 Transitional provision: enforcement notices
  9. 8 Transitional provisions: undue delays in appeals
  10. 9 Transitional provision: penalties for non-compliance

Proposed changes to this act

No one has proposed a change to this act yet.

How this law is officially changed

Solon does not know this law's official route yet. The proposal is recorded all the same, and the route appears here once its source is added.

10 provisions

Title and introductory text

2024 No. 452 (C. 28) TOWN AND COUNTRY PLANNING, ENGLAND AND WALES The Planning Act 2008 (Commencement No. 8) and Levelling-up and Regeneration Act 2023 (Commencement No. 4 and Transitional Provisions) Regulations 2024 Made 2nd April 2024 The Secretary of State makes these Regulations in exercise of the powers conferred by section 241(8) of the Planning Act 2008 and by section 255(3)(b) and (12) of the Levelling-up and Regeneration Act 2023.

Propose a change

1 Citation and interpretation

(1) These Regulations may be cited as the Planning Act 2008 (Commencement No. 8) and Levelling-up and Regeneration Act 2023 (Commencement No. 4 and Transitional Provisions) Regulations 2024. (2) In these Regulations— “the 1990 Act” means the Town and Country Planning Act 1990; “the 2008 Act” means the Planning Act 2008; “the 2023 Act” means the Levelling-up and Regeneration Act 2023.

Propose a change

2 Provisions of the 2008 Act coming into force on 25th April 2024

The following provisions of the 2008 Act come into force on 25th April 2024— (a) section 196 (determination of procedure for certain proceedings), and (b) paragraphs 1, 7, 8 and 10 to 14 of Schedule 10 (further provisions as to the procedure for certain proceedings), so far as they relate to any appeal under section 195 of the 1990 Act (appeals against refusal or failure to give decision on application) against a refusal, or failure to give a decision, of a local planning authority.

Propose a change

3 Provisions of the 2023 Act coming into force on 25th April 2024

The following provisions of the 2023 Act come into force on 25th April 2024— (a) section 103 (temporary stop notices in relation to listed buildings); (b) section 115 (time limits for enforcement); (c) section 116 (duration of temporary stop notices); (d) section 117 (enforcement warning notices); (e) section 118 (restriction on appeals against enforcement notices); (f) section 119 (undue delays in appeals); (g) section 120 (penalties for non-compliance); (h) section 122 (consultation before applying for planning permission); (i) section 124 (powers as to form and content of planning applications).

Propose a change

4 Provision of the 2023 Act coming into force on 25th July 2024

Section 105 of the 2023 Act (removal of compensation for building preservation notice) comes into force on 25th July 2024.

Propose a change

5 Transitional provision: time limits for enforcement

The amendments made to the 1990 Act by section 115 of the 2023 Act (time limits for enforcement) do not apply where— (a) in respect of a breach of planning control referred to in section 171B(1) of the 1990 Act (time limits), the operations were substantially completed, or (b) in respect of a breach of planning control referred to in section 171B(2) of the 1990 Act (time limits), the breach occurred, before the day on which that section comes into force.

Propose a change

6 Transitional provision: duration of temporary stop notices

The amendments made to the 1990 Act by section 116 of the 2023 Act (duration of temporary stop notices) do not apply where— (a) a temporary stop notice has been issued under section 171E of the 1990 Act, and (b) the temporary stop notice has not been withdrawn under section 171E(7)(c) of that Act, before the day on which that section comes into force.

Propose a change

7 Transitional provision: enforcement notices

The amendments made to the 1990 Act by section 118 of the 2023 Act (restriction on appeals against enforcement notices) do not apply where— (a) an enforcement notice has been issued under section 172 of the 1990 Act (issue of enforcement notice), and (b) the enforcement notice has not been withdrawn under section 173A of that Act (variation and withdrawal of enforcement notices), before the day on which that section comes into force.

Propose a change

8 Transitional provisions: undue delays in appeals

(1) The amendments made to the 1990 Act by section 119 of the 2023 Act (undue delays in appeals) do not apply where— (a) an enforcement notice has been issued under section 172 of the 1990 Act (issue of enforcement notice), (b) the enforcement notice has not been withdrawn under section 173A of the 1990 Act (variation and withdrawal of enforcement notices), and (c) an appeal under section 174 of the 1990 Act (appeal against enforcement notice) has been made against that notice, before the day on which that section comes into force. (2) The amendments made to the 1990 Act by section 119 of the 2023 Act (undue delays in appeals) do not apply where— (a) an application has been made to a local planning authority and determined or not determined (as the case may be) under either section 191 of the 1990 Act (certificate of lawfulness of existing use or development) or section 192 of the 1990 Act (certificate of lawfulness of proposed use or development), and (b) an appeal under either subsection (1)(a) or (1)(b) of section 195 of that Act (appeals against refusal or failure to give decision on application) has been made against that refusal or failure to give a decision, before the day on which that section comes into force.

Propose a change

9 Transitional provision: penalties for non-compliance

The amendments made to the 1990 Act by section 120 of the 2023 Act (penalties for non-compliance) apply only in relation to offences committed after the section has come into force.

Propose a change