Law

Housing and Planning Act 2016

United Kingdom · statute

Ask the law about thisMore laws of United KingdomFor machines: Markdown

Open at the publisher →

In force since 2026-10-31, as the publisher states.

Copy read on 2026-11-08. The page it was read from

Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

sha256 1bd9d81ac79e3374004f3a73624f35ee80b7ff93f5fc32a8d1b5508d67a1d13c

Contents: 206 provisions
  1. Title and introductory text
  2. 9 Definitions
  3. 10 Duty to grant planning permission etc
  4. 11 Exemption from duty
  5. 12 Further and consequential amendments
  6. 13 Introduction to this Part
  7. 14 “Banning order” and “banning order offence”
  8. 15 Application and notice of intended proceedings
  9. 16 Making a banning order
  10. 17 Duration and effect of banning order
  11. 18 Content of banning order: involvement in bodies corporate
  12. 19 Power to require information
  13. 20 Revocation or variation of banning orders
  14. 21 Offence of breach of banning order
  15. 22 Offences by bodies corporate
  16. 23 Financial penalty for breach of banning order
  17. 24 Saving for illegal contracts
  18. 25 Banned person may not hold HMO licence etc
  19. 26 Management orders following banning order
  20. 27 Prohibition on certain disposals
  21. 28 Database of rogue landlords and property agents
  22. 29 Duty to include person with banning order
  23. 30 Power to include person convicted of banning order offence
  24. 31 Procedure for inclusion under section 30
  25. 32 Appeals
  26. 33 Information to be included in the database
  27. 34 Updating
  28. 35 Power to require information
  29. 36 Removal or variation of entries made under section 30
  30. 37 Requests for exercise of powers under section 36 and appeals
  31. 38 Access to database
  32. 39 Use of information in database
  33. 40 Introduction and key definitions
  34. 41 Application for rent repayment order
  35. 42 Notice of intended proceedings
  36. 43 Making of rent repayment order
  37. 44 Amount of order: tenants
  38. 45 Amount of order: local housing authorities
  39. 46 Amount of order following conviction
  40. 46A Amount of order: supplementary
  41. 47 Enforcement of rent repayment orders
  42. 48 Duty to consider applying for rent repayment orders
  43. 49 Helping tenants apply for rent repayment orders
  44. 50 Rent repayment orders: consequential amendments
  45. 51 Housing benefit: inclusion pending abolition
  46. 51A Landlord which is body corporate: liability of directors etc
  47. 52 Interpretation of Chapter
  48. 53 Appeals from the first-tier tribunal
  49. 54 Meaning of “letting agent” and related expressions
  50. 55 Meaning of “property manager” and related expressions
  51. 56 General interpretation of Part
  52. 64 Grants by Secretary of State
  53. 65 Grants by Greater London Authority
  54. 66 Monitoring
  55. 67 Consequential changes to HCA's duty to give grants
  56. 68 Interpretation of Chapter
  57. 69 Payments to Secretary of State
  58. 70 Housing to be taken into account
  59. 71 Procedure for determinations
  60. 72 More about determinations
  61. 73 Determinations in the first year that section 69 comes into force
  62. 74 Reduction of payment by agreement
  63. 75 Set off against repayments under section 69
  64. 76 Duty to consider selling vacant higher value housing
  65. 77 Local authority disposal of housing: consent requirements
  66. 78 Set off under section 11 of Local Government Act 2003
  67. 79 Interpretation of Chapter
  68. 80 Mandatory rents for high income local authority tenants
  69. 81 Meaning of “high income” etc
  70. 82 Information about income
  71. 83 HMRC information
  72. 84 Reverting to original rent levels
  73. 85 Power to change rents and procedure for changing rents
  74. 86 Payment by local authority of increased income to Secretary of State
  75. 87 Provision of information to Secretary of State
  76. 88 Interaction with other legislation and consequential amendments
  77. 89 Private providers: policies for high income social tenants
  78. 90 HMRC information for private registered providers
  79. 91 Interpretation of Chapter
  80. 92 Reducing social housing regulation
  81. 93 Reducing local authority influence over private registered providers
  82. 94 Recovery of social housing assistance: successors in title
  83. 95 Housing administration order: providers of social housing in England
  84. 96 Objectives of housing administration
  85. 97 Objective 1: normal administration
  86. 98 Objective 2: keeping social housing in the regulated sector
  87. 99 Applications for housing administration orders
  88. 100 Powers of court
  89. 101 Housing administrators
  90. 102 Conduct of administration etc
  91. 103 Housing administrator may sell land free from planning obligations
  92. 104 Winding-up orders
  93. 105 Voluntary winding up
  94. 106 Making of ordinary administration orders
  95. 107 Administrator appointments by creditors etc
  96. 108 Enforcement of security
  97. 109 Grants and loans where housing administration order is made
  98. 110 Indemnities where housing administration order is made
  99. 111 Indemnities: repayment by registered provider etc
  100. 112 Guarantees where housing administration order is made
  101. 113 Guarantees: repayment by registered provider etc
  102. 114 Modification of this Chapter under the Enterprise Act 2002
  103. 115 Amendments to housing moratorium and consequential amendments
  104. 116 Interpretation of Chapter
  105. 117 Application of Part to Northern Ireland
  106. 122 Electrical safety standards for residential properties let by landlords
  107. 123 Electrical safety standards: enforcement
  108. 124 Assessment of accommodation needs
  109. 126 Financial penalty as alternative to prosecution under Housing Act 2004
  110. 128 Tenancy deposit information
  111. 129 Use of information obtained for certain other statutory purposes
  112. 130 Tenants' associations: power to request information about tenants
  113. 131 Limitation of administration charges: costs of proceedings
  114. 132 Estate agents: lead enforcement authority
  115. 133 Power to require property agents to join client money protection schemes
  116. 134 Client money protection schemes: approval or designation
  117. 135 Enforcement of client money protection scheme regulations
  118. 136 Enfranchisement and extension of long leaseholds: calculations
  119. 137 Redemption price for rentcharges
  120. 139 Designation of neighbourhood areas
  121. 140 Timetable in relation to neighbourhood development orders and plans
  122. 141 Making neighbourhood development orders and plans: intervention powers
  123. 142 Local planning authority to notify neighbourhood forum of applications
  124. 143 Power to direct amendment of local development scheme
  125. 144 Power to give direction to examiner of development plan document
  126. 145 Intervention by Secretary of State
  127. 146 Secretary of State's default powers
  128. 147 Default powers exercisable by Mayor of London or combined authority
  129. 148 Costs of independent examinations held by Secretary of State
  130. 149 Planning powers of the Mayor of London
  131. 150 Permission in principle for development of land
  132. 151 Local planning authority to keep register of particular kinds of land
  133. 152 Approval condition where development order grants permission for building
  134. 153 Planning applications that may be made directly to Secretary of State
  135. 154 Planning freedoms: right for local areas to request alterations to planning system
  136. 156 Local planning authorities: information about neighbourhood development plans
  137. 157 Planning applications etc: setting of fees
  138. 160 Development consent for projects that involve housing
  139. 161 Processing of planning applications by alternative providers
  140. 162 Regulations under section 161: general
  141. 163 Regulations under section 161: fees and payments
  142. 164 Regulations under section 161: information
  143. 165 Review of minimum energy performance requirements
  144. 166 Designation of urban development areas: procedure
  145. 167 Establishment of urban development corporations: procedure
  146. 168 Sections 166 and 167: consequential repeals
  147. 169 Designation of new town areas and establishment of corporations: procedure
  148. 170 New towns: objects of development corporations in England
  149. 171 Sustainable drainage
  150. 172 Right to enter and survey land
  151. 173 Warrant authorising use of force to enter and survey land
  152. 174 Notice of survey and copy of warrant
  153. 175 Enhanced authorisation procedures etc. for certain surveys
  154. 176 Right to compensation after entry on or survey of land
  155. 177 Offences in connection with powers to enter land
  156. 178 Right to enter and survey or value Crown land
  157. 179 Amendments to do with sections 172 to 178
  158. 180 Timetable for confirmation of compulsory purchase order
  159. 181 Confirmation by inspector
  160. 182 Time limits for notice to treat or general vesting declaration
  161. 183 Notice of general vesting declaration procedure
  162. 184 Earliest vesting date under general vesting declaration
  163. 185 No general vesting declaration after notice to treat
  164. 186 Extended notice period for taking possession following notice to treat
  165. 187 Counter-notice requiring possession to be taken on specified date
  166. 188 Agreement to extend notice period for possession following notice to treat
  167. 189 Corresponding amendments to the New Towns Act 1981
  168. 190 Abolition of alternative possession procedure following notice to treat
  169. 191 Extended notice period for taking possession following vesting declaration
  170. 192 Making a claim for compensation
  171. 193 Compensation after withdrawal of notice to treat
  172. 194 Making a request for advance payment of compensation
  173. 195 Power to make and timing of advance payment
  174. 196 Interest on advance payments of compensation
  175. 197 Repayment of advance payment where no compulsory purchase
  176. 198 Repayment of payment to mortgagee if land not acquired
  177. 199 Objection to division of land
  178. 200 Objection to division of land: blight notices
  179. 201 Power to quash decision to confirm compulsory purchase order
  180. 202 Extension of compulsory purchase time limit during challenge
  181. 203 Power to override easements and other rights
  182. 204 Compensation for overridden easements etc
  183. 205 Interpretation of sections 203 and 204
  184. 206 Amendments to do with sections 203 and 204
  185. 212 Power to make transitional provision
  186. 213 Power to make consequential provision
  187. 214 Regulations: general
  188. 215 Extent
  189. 216 Commencement
  190. 217 Short title
  191. SCHEDULE 1 Financial penalty for breach of banning order
  192. SCHEDULE 2 Banned person may not hold HMO licence etc
  193. SCHEDULE 3 Management orders following banning order
  194. SCHEDULE 4 Reducing social housing regulation
  195. SCHEDULE 5 Conduct of housing administration: companies
  196. SCHEDULE 6 Amendments to housing moratorium and consequential amendments
  197. SCHEDULE 9 Financial penalty as alternative to prosecution under Housing Act 2004
  198. SCHEDULE 10 Enfranchisement and extension of long leaseholds: calculations
  199. SCHEDULE 11 Default powers exercisable by Mayor of London or combined authority: Schedule to be inserted in the Planning and Compulsory Purchase Act 2004
  200. SCHEDULE 12 Permission in principle for development of land: minor and consequential amendments
  201. SCHEDULE 14 Right to enter and survey land: consequential amendments
  202. SCHEDULE 15 Notice of general vesting declaration procedure
  203. SCHEDULE 16 Abolition of alternative possession procedure following notice to treat
  204. SCHEDULE 17 Objection to division of land following notice to treat
  205. SCHEDULE 18 Objection to division of land following vesting declaration
  206. SCHEDULE 19 Amendments to do with sections 203 and 204

Proposed changes to this act

No one has proposed a change to this act yet.

206 provisions

140 Timetable in relation to neighbourhood development orders and plans

(1) In Schedule 4B to the Town and Country Planning Act 1990 (process for making of neighbourhood development orders), after paragraph 13 insert— 13A Regulations may make provision— (a) requiring any prescribed action falling to be taken by the local planning authority under paragraph 12 or 13 to be taken by a prescribed date; (b) imposing time limits for the submission of representations invited under paragraph 13(1). (2) In section 61E of that Act (neighbourhood development orders), in subsection (4)(b), after “as soon as reasonably practicable after the referendum is held” insert “ and, in any event, by such date as may be prescribed ”. (3) In section 38A of the Planning and Compulsory Purchase Act 2004 (meaning of “neighbourhood development plan”), in subsection (4)(b), after “as soon as reasonably practicable after the referendum is held” insert “ and, in any event, by such date as may be prescribed ”.

Propose a change

141 Making neighbourhood development orders and plans: intervention powers

(1) In Schedule 4B to the Town and Country Planning Act 1990, before paragraph 14 insert— Intervention powers of Secretary of State 13B (1) This paragraph applies where the qualifying body requests the Secretary of State to intervene under this paragraph and— (a) the local planning authority have failed, by the applicable date prescribed under paragraph 13A, to take a decision as to whether a referendum is (or referendums are) to be held on the making of a neighbourhood development order, (b) a recommendation made under paragraph 10(2) is not followed by the authority, or (c) the authority make any modification under paragraph 12(5) that is not— (i) a modification recommended under paragraph 10(2)(b), (ii) a modification that the authority consider needs to be made to secure that the draft order does not breach, and is otherwise compatible with, EU obligations, (iii) a modification that the authority consider needs to be made to secure that the draft order is compatible with the Convention rights, or (iv) a modification for the purpose of correcting an error. (2) The Secretary of State may exercise functions of the local planning authority under paragraph 12(2) and (3) and— (a) if satisfied that paragraph (a) or (b) of paragraph 12(4) applies, may direct the authority to make arrangements for a referendum (or referendums) to be held on the making of a neighbourhood development order; (b) if not so satisfied, may direct the authority to refuse the proposal. (3) The Secretary of State may direct the authority to take the actions referred to in paragraph 12(8) and (9). (4) If by reason (wholly or partly) of new evidence or a new fact, or a different view taken by the Secretary of State as to a particular fact, the Secretary of State proposes to direct the local planning authority to act in a way that is not in accordance with what was recommended by the examiner— (a) the Secretary of State may require the authority to notify prescribed persons of the proposed direction (and the reason for it) and invite representations; (b) the Secretary of State may also require them to refer the issue to independent examination. (5) The order on which a referendum is (or referendums are) to be held by virtue of sub-paragraph (2)(a) is the draft order subject to such modification (if any) as the Secretary of State or the local planning authority consider appropriate. (6) The only modifications the local planning authority may make under sub-paragraph (5) are— (a) modifications that the authority consider need to be made to secure that the draft order does not breach, and is otherwise compatible with, EU obligations, (b) modifications that the authority consider need to be made to secure that the draft order is compatible with the Convention rights, and (c) modifications for the purpose of correcting errors. 13C Regulations may make provision supplementing that made by paragraph 13B; and the regulations may in particular— (a) prescribe the form and content of a request by the qualifying body under paragraph 13B(1) and the date by which it must be made; (b) confer power on the Secretary of State to direct a local planning authority to refrain from taking any action specified in the direction that they would otherwise be required or entitled to take under paragraph 12 or 13; (c) make provision under which decisions falling to be made by the Secretary of State under paragraph 13B may be made instead by a person appointed by the Secretary of State for the purpose (an “inspector”); (d) prescribe matters that the Secretary of State or an inspector must take into account in making a decision; (e) require a local planning authority to provide prescribed information to the Secretary of State or to an inspector; (f) make provision about examinations carried out by virtue of paragraph 13B(4)(b) (including any provision of a kind mentioned in paragraph 11(2)); (g) make provision (in addition to that made by paragraph 13B(4)(b)) for the holding of an examination, and for the payment by a local planning authority of remuneration and expenses of the examiner; (h) provide for the Secretary of State, or a local planning authority on the direction of the Secretary of State, to notify to prescribed persons and to publish— (i) prescribed decisions made by the Secretary of State under paragraph 13B, (ii) the reasons for making those decisions, and (iii) other prescribed matters relating to those decisions. (2) In paragraph 14 of that Schedule (referendum), in sub-paragraph (1), after “as a result of paragraph 12(4)” insert “ or a direction under paragraph 13B(2)(a) ”. (3) In section 61N of that Act (legal challenges in relation to neighbourhood development orders), in subsection (2), before “only if” insert “ or paragraph 13B of that Schedule (intervention powers of Secretary of State) ”.

Propose a change

142 Local planning authority to notify neighbourhood forum of applications

In Schedule 1 to the Town and Country Planning Act 1990 (local planning authorities: distribution of functions), after paragraph 8 insert— 8A (1) A local planning authority who have the function of determining applications for planning permission or permission in principle shall, if requested to do so by a neighbourhood forum for an area which (or any part of which) is situated in the authority's area, notify the neighbourhood forum of— (a) any relevant planning application; and (b) any alteration to that application accepted by the authority. (2) In this paragraph— “neighbourhood forum” means an organisation or body designated as such under section 61F; “relevant planning application” means an application which— relates to land in the area for which the neighbourhood forum is designated; and is an application for— planning permission or permission in principle; or approval of a matter reserved under an outline planning permission within the meaning of section 92. (3) Sub-paragraphs (3) to (6) of paragraph 8 have effect for the purposes of this paragraph, any reference to a parish council being read as a reference to a neighbourhood forum.

Propose a change

143 Power to direct amendment of local development scheme

(1) In section 15 of the Planning and Compulsory Purchase Act 2004 (local development scheme), before subsection (4) insert— (3A) If a local planning authority have not prepared a local development scheme, the Secretary of State or the Mayor of London may— (a) prepare a local development scheme for the authority, and (b) direct the authority to bring that scheme into effect. (2) In subsections (4) and (8AA) of that section, for “effective coverage” substitute “ full and effective coverage (both geographically and with regard to subject matter) ”. (3) In subsections (4A)(a), (5), (6), (6A) and (6B)(a) of that section, after “under subsection” insert “ (3A) or ”.

Propose a change

144 Power to give direction to examiner of development plan document

In section 20 of the Planning and Compulsory Purchase Act 2004 (independent examination), after subsection (6) insert— (6A) The Secretary of State may by notice to the person appointed to carry out the examination— (a) direct the person not to take any step, or any further step, in connection with the examination of the development plan document, or of a specified part of it, until a specified time or until the direction is withdrawn; (b) require the person— (i) to consider any specified matters; (ii) to give an opportunity, or further opportunity, to specified persons to appear before and be heard by the person; (iii) to take any specified procedural step in connection with the examination. In this subsection “specified” means specified in the notice.

Propose a change

145 Intervention by Secretary of State

(1) In section 21 of the Planning and Compulsory Purchase Act 2004 (intervention by Secretary of State), in subsection (3), after “if” insert “ or to the extent that ”. (2) In subsection (5) of that section— (a) in paragraph (a), after “until the Secretary of State gives his decision” insert “ , or withdraws the direction ”; (b) for paragraph (b) substitute— (b) if the direction is given, and not withdrawn, before the authority have submitted the document under section 20(1), the Secretary of State must hold an independent examination; ; (c) in paragraph (c), for “he” substitute “ , and is not withdrawn before those recommendations are made, the person ”; (d) for paragraph (d) substitute— (d) the document has no effect unless the document or (as the case may be) the relevant part of it has been approved by the Secretary of State, or the direction is withdrawn. (3) After that subsection insert— (5A) Subsections (4) to (7C) of section 20 apply to an examination held under subsection (5)(b), the reference to the local planning authority in subsection (7C) of that section being read as a reference to the Secretary of State. (5B) For the purposes of subsection (5)(d) the “relevant part” of a development plan document is the part that— (a) is covered by a direction under subsection (4) which refers to only part of the document, or (b) continues to be covered by a direction under subsection (4) following the partial withdrawal of the direction. (4) At the end of that section insert— (11) The local planning authority must reimburse the Secretary of State for any expenditure incurred by the Secretary of State under this section that is specified in a notice given to the authority by the Secretary of State. (5) After that section insert— Temporary direction pending possible use of intervention powers 21A (1) If the Secretary of State is considering whether to give a direction to a local planning authority under section 21 in relation to a development plan document or other local development document, he may direct the authority not to take any step in connection with the adoption of the document— (a) until the time (if any) specified in the direction, or (b) until the direction is withdrawn. (2) A document to which a direction under this section relates has no effect while the direction is in force. (3) A direction given under this section in relation to a document ceases to have effect if a direction is given under section 21 in relation to that document.

Propose a change

146 Secretary of State's default powers

For section 27 of the Planning and Compulsory Purchase Act 2004 substitute— Secretary of State's default powers 27 (1) This section applies if the Secretary of State thinks that a local planning authority are failing or omitting to do anything it is necessary for them to do in connection with the preparation, revision or adoption of a development plan document. (2) The Secretary of State may— (a) prepare or revise (as the case may be) the document, or (b) give directions to the authority in relation to the preparation or revision of the document. (3) The Secretary of State must either— (a) hold an independent examination, or (b) direct the authority to submit the document for independent examination. (4) The Secretary of State must either— (a) publish the recommendations and reasons of the person appointed to hold the examination, or (b) give directions to the authority in relation to publication of those recommendations and reasons. (5) The Secretary of State may— (a) approve the document, or approve it subject to specified modifications, as a local development document, (b) direct the authority to consider adopting the document by resolution of the authority as a local development document, or (c) (except where it was prepared or revised by the Secretary of State under subsection (2)(a)) reject the document. (6) Subsections (4) to (7C) of section 20 apply (subject to subsection (7) below) to an examination held under subsection (3)(a), the reference to the local planning authority in subsection (7C) of that section being read as a reference to the Secretary of State. (7) Subsections (5)(c), (7)(b)(ii) and (7B)(b) of section 20 do not apply to an independent examination held— (a) under subsection (3)(a), or (b) in response to a direction under subsection (3)(b), in respect of a document prepared or revised by the Secretary of State under subsection (2)(a). (8) The Secretary of State must give reasons for anything he does in pursuance of subsection (2) or (5). (9) The authority must reimburse the Secretary of State for any expenditure he incurs in connection with anything— (a) which is done by him under subsection (2)(a), and (b) which the authority failed or omitted to do as mentioned in subsection (1).

Propose a change

147 Default powers exercisable by Mayor of London or combined authority

(1) After section 27 of the Planning and Compulsory Purchase Act 2004 insert— Default powers exercisable by Mayor of London or combined authority 27A Schedule A1 (default powers exercisable by Mayor of London or combined authority) has effect. (2) Before Schedule 1 to that Act insert, as Schedule A1, the Schedule set out in Schedule 11 to this Act. (3) In section 17 of that Act (local development documents), at the end of subsection (8) insert— (c) is approved by the Mayor of London under paragraph 2 of Schedule A1; (d) is approved by a combined authority under paragraph 6 of that Schedule.

Propose a change

148 Costs of independent examinations held by Secretary of State

(1) Section 303A of the Town and Country Planning Act 1990 (responsibility of local planning authorities for costs of holding certain inquiries etc) is amended as follows. (2) In subsection (1A), after “section 20” insert “ , 21(5)(b), 27(3)(a) ”. (3) For subsection (9A) substitute— (9A) A reference to a local planning authority causing a qualifying procedure to be carried out includes a reference to the case where under the Planning and Compulsory Purchase Act 2004— (a) the local planning authority are required to submit a document to the appropriate authority for independent examination, or (b) the Secretary of State holds an independent examination in relation to a document prepared by the local planning authority, or by the Secretary of State under section 27(2)(a) of that Act.

Propose a change

149 Planning powers of the Mayor of London

(1) In section 2A of the Town and Country Planning Act 1990 (power of Mayor of London to decide applications of potential strategic importance), in subsection (6), for “areas, and” substitute areas; (aa) may prescribe matters by reference to the spatial development strategy, or a development plan document (within the meaning of Part 2 of the Planning and Compulsory Purchase Act 2004), as it has effect from time to time; . (2) In section 74 of that Act (directions etc as to method of dealing with applications), in subsection (1B)— (a) in paragraph (a), for “London borough to refuse” substitute London borough— (i) to consult with the Mayor of London before granting or refusing an application for planning permission, or permission in principle, that is an application of a prescribed description, or (ii) to refuse ; (b) in paragraph (c), for “such a direction;” substitute “ a direction given by virtue of paragraph (a)(ii). ”; (c) omit the words after that paragraph. (3) After that subsection insert— (1BA) In subsection (1B) “prescribed” means— (a) prescribed by a development order, or (b) specified in directions made under a development order by the Secretary of State or the Mayor of London. (1BB) Matters prescribed under subsection (1B) by a development order may be prescribed by reference to the spatial development strategy, or a development plan document (within the meaning of Part 2 of the Planning and Compulsory Purchase Act 2004), as it has effect from time to time.

Propose a change

150 Permission in principle for development of land

(1) After section 58 of the Town and Country Planning Act 1990 insert— Permission in principle Permission in principle: general 58A (1) Permission in principle may be granted for housing-led development of land in England as provided in section 59A. (2) Permission in principle may not be granted for development consisting of the winning and working of minerals. (3) For the effect of permission in principle, see section 70(2ZZA) to (2ZZC) (application for technical details consent must be determined in accordance with permission in principle, except after a prescribed period). (4) A reference to permission in principle in any provision of this Act in its application to land in Wales, or in its application to functions of the Welsh Ministers or other authorities in Wales, is to be ignored. (2) After section 59 of that Act insert— Development orders: permission in principle 59A (1) A development order may either— (a) itself grant permission in principle, in relation to land in England that is allocated for development in a qualifying document (whether or not in existence when the order is made) for development of a prescribed description; or (b) provide for the granting by a local planning authority in England, on application to the authority in accordance with the provisions of the order, of permission in principle for development of a prescribed description. (2) In this section— “prescribed” means prescribed in a development order; “qualifying document” means a document, as it has effect from time to time, which— falls within subsection (3), indicates that the land in question is allocated for development for the purposes of this section, and contains prescribed particulars in relation to the land allocated and the kind of development for which it is allocated. (3) The following documents fall within this subsection— (a) a register maintained in pursuance of regulations under section 14A of the Planning and Compulsory Purchase Act 2004 (“the 2004 Act”); (b) a development plan document within the meaning of Part 2 of the 2004 Act (see section 37 of that Act); (c) a neighbourhood development plan within the meaning given by section 38A of the 2004 Act. (4) Permission in principle granted by a development order takes effect— (a) when the qualifying document takes effect, if the land in question is allocated for development in the document at that time; (b) otherwise, when the qualifying document is revised so that the land in question is allocated for development. But a development order may provide that, if the local planning authority so directs, permission in principle does not take effect until the date specified by the local planning authority in the direction. (5) For the purposes of subsection (4)(a)— (a) a register maintained in pursuance of regulations under section 14A of the 2004 Act takes effect when it is first published; (b) a development plan document takes effect when it is adopted or approved under Part 2 of the 2004 Act; (c) a neighbourhood development plan takes effect when it is made by the local planning authority. (6) Permission in principle granted by a development order is not brought to an end by the qualifying document ceasing to have effect or being revised. (7) Permission in principle granted by a development order ceases to have effect on the expiration of— (a) five years beginning with the date on which it takes effect; or (b) such other period (whether longer or shorter) beginning with that date as the local planning authority may direct. (8) Permission in principle granted by a local planning authority ceases to have effect on the expiration of— (a) three years beginning with the date on which it takes effect; or (b) such other period (whether longer or shorter) beginning with that date as the local planning authority may direct. (9) The Secretary of State may by regulations amend subsection (7)(a) or (8)(a) by substituting a shorter period for the period for the time being specified there. (10) A development order— (a) may make provision in relation to an application for planning permission for development of land in respect of which permission in principle has been granted; (b) may require the local planning authority to prepare, maintain and publish a register containing prescribed information as to permissions in principle granted by a development order. (11) In exercising a power of direction conferred by virtue of subsection (4), or conferred by subsection (7)(b) or (8)(b), a local planning authority must have regard to the provisions of the development plan and any other material considerations. (12) In exercising any other function exercisable by virtue of this section, or in exercising any function in relation to an application for planning permission for development of land in respect of which permission in principle has been granted, a local planning authority must have regard to any guidance issued by the Secretary of State. (13) In relation to an application for permission in principle which under any provision of this Part is made to, or determined by, the Secretary of State instead of the local planning authority, a reference in subsection (1) or (8) to a local planning authority has effect (as necessary) as a reference to the Secretary of State. (3) In section 70 of that Act (determination of applications: general considerations)— (a) after subsection (1) insert— (1A) Where an application is made to a local planning authority for permission in principle— (a) they may grant permission in principle; or (b) they may refuse permission in principle. ; (b) after subsection (2) insert— (2ZZA) The authority must determine an application for technical details consent in accordance with the relevant permission in principle. This is subject to subsection (2ZZC). (2ZZB) An application for technical details consent is an application for planning permission that— (a) relates to land in respect of which permission in principle is in force, (b) proposes development all of which falls within the terms of the permission in principle, and (c) particularises all matters necessary to enable planning permission to be granted without any reservations of the kind referred to in section 92. (2ZZC) Subsection (2ZZA) does not apply where— (a) the permission in principle has been in force for longer than a prescribed period, and (b) there has been a material change of circumstances since the permission came into force. “Prescribed” means prescribed for the purposes of this subsection in a development order. (4) In section 333 of that Act (regulations and orders), after subsection (3) insert— (3ZA) No regulations may be made under section 59A(9) unless a draft of the instrument containing the regulations has been laid before, and approved by a resolution of, each House of Parliament. (5) Schedule 12 (permission in principle for development of land: minor and consequential amendments) has effect.

Propose a change

151 Local planning authority to keep register of particular kinds of land

(1) In Part 2 of the Planning and Compulsory Purchase Act 2004 (local development), after section 14 insert— Register Register of land 14A (1) The Secretary of State may make regulations requiring a local planning authority in England to prepare, maintain and publish a register of land within (or partly within) the authority's area which— (a) is of a prescribed description, or (b) satisfies prescribed criteria. (2) The regulations may require the register to be kept in two or more parts. A reference to the register in the following subsections includes a reference to a prescribed part of the register. (3) The regulations may make provision permitting the local planning authority to enter in the register land within (or partly within) the authority's area which— (a) is of a prescribed description or satisfies prescribed criteria, and (b) is not required by the regulations to be entered in the register. (4) The regulations may— (a) require or authorise a local planning authority to carry out consultation and other procedures in relation to entries in the register; (b) specify descriptions of land that are not to be entered in the register; (c) confer a discretion on a local planning authority, in prescribed circumstances, not to enter in the register land of a prescribed description that the authority would otherwise be required to enter in it; (d) require a local planning authority exercising the discretion referred to in paragraph (c) to explain why they have done so; (e) specify information to be included in the register; (f) make provision about revising the register. (5) The regulations may specify a description of land by reference to a description in national policies and advice. (6) The regulations may confer power on the Secretary of State to require a local planning authority— (a) to prepare or publish the register, or to bring the register up to date, by a specified date; (b) to provide the Secretary of State with specified information, in a specified form and by a specified date, in relation to the register. In this subsection “specified” means specified by the Secretary of State. (7) In exercising their functions under the regulations, a local planning authority must have regard to— (a) the development plan; (b) national policies and advice; (c) any guidance issued by the Secretary of State for the purposes of the regulations. (8) In this section “national policies and advice” means national policies and advice contained in guidance issued by the Secretary of State (as it has effect from time to time). (2) In section 33 of that Act (power to direct that Part 2 of that Act does not apply to the area of an urban development corporation), for “that this Part does not apply” substitute that the provisions of— (a) this Part, or (b) any particular regulations made under section 14A, do not apply .

Propose a change

152 Approval condition where development order grants permission for building

(1) In section 60 of the Town and Country Planning Act 1990 (permission granted by development order), after subsection (1) insert— (1A) Without prejudice to the generality of subsection (1), where planning permission is granted by a development order for building operations in England, the order may require the approval of the local planning authority, or the Secretary of State, to be obtained— (a) for those operations, or (b) with respect to any matters that relate to those operations, or to the use of the land in question following those operations, and are specified in the order. (2) In subsection (2) of that section, after “any buildings” insert “ in Wales ”. (3) In subsection (2B) of that section, for “subsection (1)” substitute “ subsections (1) and (1A) ”. (4) In section 70A of that Act (power to decline to determine subsequent application), in subsection (5)(b), for “section 60(2)” substitute “ section 60(1A), (2) ”.

Propose a change

153 Planning applications that may be made directly to Secretary of State

(1) In section 62A of the Town and Country Planning Act 1990 (when application may be made directly to Secretary of State), in subsection (1), for paragraphs (a) and (b) substitute— (a) the local planning authority concerned is designated by the Secretary of State for applications of a description specified in the designation; and (b) the application falls within that description. (2) After that subsection insert— (1A) Only prescribed descriptions of application may be specified in a designation under subsection (1). (3) For subsection (2) of that section substitute— (2) In this section “relevant application” means— (a) an application for planning permission, or permission in principle, for the development of land in England, or (b) an application for approval of a matter that, as defined by section 92, is a reserved matter in the case of an outline planning permission for the development of land in England, but does not include an application of the kind described in section 73(1) or an application of a description excluded by regulations. (4) In subsection (3)(a)(i) of that section omit “, or for conservation area consent,”. (5) In section 62B of that Act (designation for the purposes of section 62A), after subsection (1) insert— (1A) A document to which subsection (2) applies may set out different criteria for each description of application prescribed under section 62A(1A).

Propose a change

154 Planning freedoms: right for local areas to request alterations to planning system

(1) If the following conditions are met, the Secretary of State may by regulations make a planning freedoms scheme, having effect for a specified period, in relation to a specified planning area in England. A “planning freedoms scheme” is a scheme that disapplies or modifies specified planning provisions in order to facilitate an increase in the amount of housing in the planning area concerned. (2) The first condition is that the relevant planning authority or authorities have requested the Secretary of State to make a planning freedoms scheme for their area. (3) The second condition is that the Secretary of State is satisfied— (a) that there is a need for a significant increase in the amount of housing in the planning area concerned, (b) that the planning freedoms scheme will contribute to such an increase, and (c) that adequate consultation has been carried out. (4) The third condition is that— (a) the relevant planning authority or authorities have prepared a summary of the views expressed in the consultation referred to in subsection (3)(c), and (b) the Secretary of State has considered that summary. (5) For the purposes of subsection (3)(c) consultation is “adequate” only if— (a) the relevant authority or authorities publish an explanation of what the proposed planning freedoms scheme is expected to involve, and (b) persons in the planning area concerned, and other persons likely to be affected, have a reasonable opportunity to communicate their views about the proposed scheme. (6) The Secretary of State may decide to restrict the number of planning freedoms schemes in force at any one time (and accordingly is not required to make a scheme merely because the conditions in this section are met). (7) The Secretary of State may by regulations bring a planning freedoms scheme to an end, and must do so if the relevant planning authority or, as the case may be, any of the relevant planning authorities so request. (8) In this section— “planning area” means the area of a local planning authority, or an area comprising two or more adjoining areas of local planning authorities; “planning provision” means a provision to do with planning that is contained in or made under any Act; “relevant planning authority” means the local planning authority for an area that is or forms part of a planning area; “specified” means specified in regulations under subsection (1).

Propose a change

156 Local planning authorities: information about neighbourhood development plans

After section 75ZA of the Town and Country Planning Act 1990 (inserted by section 155 above) insert— Information about neighbourhood development plans 75ZB (1) This section applies where— (a) a report of the kind mentioned in section 75ZA(1) recommends the grant of planning permission or permission in principle, and (b) the proposed development is in an area for which a neighbourhood development plan (made under section 38A of the Planning and Compulsory Purchase Act 2004) is in force. (2) The report must— (a) set out how the plan was taken into account in making the recommendation, and (b) identify any points of conflict between the plan and the recommendation.

Propose a change

157 Planning applications etc: setting of fees

In section 303 of the Town and Country Planning Act 1990 (fees for planning applications etc), after subsection (8) insert— (8A) If a draft of regulations of the Secretary of State under this section would, apart from this subsection, be treated as a hybrid instrument for the purposes of the standing orders of either House of Parliament, it is to proceed in that House as if it were not a hybrid instrument.

Propose a change

160 Development consent for projects that involve housing

(1) Section 115 of the Planning Act 2008 (development for which development consent may be granted) is amended as follows. (2) At the end of subsection (1) insert , or (c) related housing development. (3) In subsection (2)(b), for “is not” substitute “ does not consist of or include ”. (4) Before subsection (5) insert— (4B) Related housing development” means development which— (a) consists of or includes the construction or extension of one or more dwellings, (b) is on the same site as, or is next to or close to, any part of the development within subsection (1)(a), or is otherwise associated with that development (or any part of it), (c) is to be carried out wholly in England, and (d) meets the condition in subsection (4C). (4C) Development meets the condition in this subsection if the development within subsection (1)(a) to which it is related is to be carried out in one or more of the following areas— (a) England; (b) waters adjacent to England up to the seaward limits of the territorial sea. (5) In subsection (5), after “associated development” insert “ or related housing development ”. (6) At the end insert— (7) The Secretary of State, in deciding an application for an order granting development consent for development that includes related housing development, must take into account any matters set out in guidance published by the Secretary of State.

Propose a change

161 Processing of planning applications by alternative providers

(1) The Secretary of State may by regulations provide for temporary arrangements in particular areas in England to test the practicality and desirability of competition in the processing (but not determining) of applications to do with planning. (2) The regulations may make provision— (a) for an application for planning permission that falls to be determined by a specified local planning authority in England to be processed, if the applicant so chooses, not by that authority but by a designated person; (b) for any connected application also to be processed by a designated person and not by that authority. (3) The regulations must specify a period after which any such provision ceases to apply. That period (whether as originally specified or as subsequently extended) must end no later than five years after the first regulations under this section come into force. (4) The Secretary of State must— (a) review the operation and effectiveness of any arrangements made under the regulations; (b) no later than 12 months after the date when the arrangements (or the last of them) cease to have effect— (i) lay a report before each House of Parliament, or (ii) make a statement to the House of Parliament of which that Secretary of State is a member, setting out the results and conclusions of the review. (5) The regulations may provide that— (a) they apply only to applications that relate to development of a specified description; (b) designations of persons by the Secretary of State (see subsection (13)) may be made so as to apply only in relation to applications that relate to development of a specified description. (6) The regulations may— (a) apply or disapply, in relation to England, any enactment about planning; (b) modify the effect of any such enactment in relation to England. (7) The regulations may not contain anything that allows or requires, or could allow or require, the responsible planning authority's duty to determine an application to be carried out, to any extent, by a designated person on the authority's behalf. (8) Nothing said or done by a designated person appointed under the regulations to process an application is binding on the responsible planning authority when determining the application. (9) Before making the first regulations under this section the Secretary of State must consult such representatives of local planning authorities, and such other persons, as the Secretary of State thinks fit. (10) Sections 162 to 164, which set out matters that may be included in regulations under this section, do not limit the power in section 214(6) (to make supplementary provision etc). (11) For the purposes of this group of sections (that is, this section and sections 162 to 164), processing an application means taking any action in relation to the application (other than determining it) of a kind that— (a) might otherwise be taken by or for the responsible planning authority, and (b) is specified in the regulations. (12) In this group of sections “connected application”, in relation to an application for planning permission that is to be or has been processed by a designated person under the regulations (“the main application”), means— (a) an application for approval of a matter reserved under an outline planning permission within the meaning of section 92 of the Town and Country Planning Act 1990 (where the main application resulted in the grant of such permission), or (b) an application of a specified description, made under or by virtue of an enactment about planning, that relates to some or all of the land to which the main application relates. (13) In this group of sections “designated person” means a person— (a) who is designated by the Secretary of State in accordance with the regulations, and (b) whose designation has not been withdrawn in accordance with the regulations. The Secretary of State may designate a local planning authority. (14) In this group of sections— “local planning authority” has the same meaning as in the Town and Country Planning Act 1990; “planning permission” means planning permission under Part 3 of that Act; “responsible planning authority”, in relation to an application for planning permission or a connected application, means the local planning authority responsible for determining the application; “specified” means specified in regulations under this section.

Propose a change

162 Regulations under section 161: general

(1) Regulations under section 161 may— (a) require a designated person (subject to any specified exceptions) to process an application for planning permission if chosen to do so by an applicant; (b) provide that, where an application for planning permission is to be or has been processed by a designated person, any connected application must (subject to any specified exceptions) also be processed by that person; (c) allow a responsible planning authority to take over the processing of an application for planning permission, or a connected application, in specified circumstances. (2) The regulations may make provision about— (a) eligibility to act as a designated person; (b) the capacity of a local planning authority to act as a designated person; (c) actions to be taken or procedures to be followed— (i) by persons making applications for planning permission or connected applications, (ii) by designated persons, or (iii) by responsible planning authorities, and periods within which the actions or procedures are to be taken or followed; (d) matters to be considered by designated persons or responsible planning authorities; (e) performance standards for designated persons; (f) the investigation of complaints or concerns about designated persons; (g) cases where a person ceases to be a designated person or where a designated person is unable to continue processing an application. (3) The provision that may be made under subsection (2)(c) includes provision requiring a designated person to provide assistance to the responsible planning authority in connection with— (a) any appeal against the authority's determination of the application; (b) any application to the court made in relation to that determination. (4) The provision that may be made under subsection (2)(f) includes— (a) provision about the payment of compensation; (b) provision for a designated person to be required to indemnify the responsible authority for any compensation that the authority is required to pay; (c) provision applying anything in Part 3 of the Local Government Act 1974 (local government administration) with or without modifications. (5) The regulations may confer powers on the Mayor of London , a mayor of a mayoral combined authorities or a mayoral combined county authority or the Secretary of State in cases where a direction is given under section 2A or 77 of the Town and Country Planning Act 1990 (“call-in” directions). (6) In this section, “mayoral combined authority” and “mayoral combined county authority” have the same meaning as in the Town and Country Planning Act 1990 (see section 336 of that Act).

Propose a change

163 Regulations under section 161: fees and payments

(1) Regulations under section 161 may make provision about— (a) the setting, publication and charging of fees by designated persons or responsible planning authorities; (b) the refunding of fees, by designated persons or responsible planning authorities, in specified circumstances. (2) The provision that may be made under subsection (1)(a) includes provision giving power to the Secretary of State to prevent the charging of fees that he or she considers excessive. (3) The provision that may be made under subsection (1)(b) includes provision requiring a designated person or a responsible planning authority to refund to an applicant some or all of a fee paid by the applicant to a designated person where the person or the authority fails to do a particular thing within a specified period. (4) The regulations may authorise the making of payments by the Secretary of State to local planning authorities or designated persons.

Propose a change

164 Regulations under section 161: information

(1) Regulations under section 161 may make provision— (a) requiring responsible planning authorities to disclose information to designated persons; (b) requiring designated persons to disclose information to responsible planning authorities or to other designated persons; (c) restricting the uses to which information disclosed by virtue of paragraph (a) or (b) may be put; (d) restricting further disclosure of such information. (2) The regulations may make provision for designated persons or responsible planning authorities to be required to provide information to the Secretary of State.

Propose a change

165 Review of minimum energy performance requirements

After section 2B of the Building Act 1984 insert— Duty to review minimum energy performance requirements Review of minimum energy performance requirements 2C The Secretary of State must carry out a review of any minimum energy performance requirements approved by the Secretary of State under building regulations in relation to dwellings in England.

Propose a change

166 Designation of urban development areas: procedure

(1) Section 134 of the Local Government, Planning and Land Act 1980 (urban development areas) is amended as follows. (2) After subsection (1) insert— (1A) Before making an order under subsection (1) in relation to land in England, the Secretary of State must consult the following persons— (a) persons who appear to the Secretary of State to represent those living within, or in the vicinity of, the proposed urban development area; (b) persons who appear to the Secretary of State to represent businesses with any premises within, or in the vicinity of, the proposed urban development area; (c) each local authority for an area which falls wholly or partly within the proposed urban development area; and (d) any other person whom the Secretary of State considers it appropriate to consult. (3) For subsection (4) substitute— (4) A statutory instrument containing an order made by the Secretary of State under subsection (1) does not have effect until approved by a resolution of each House of Parliament. (4A) If a draft of an instrument containing an order by the Secretary of State under subsection (1) would, but for this subsection, be treated for the purposes of the standing orders of either House of Parliament as a hybrid instrument, it is to proceed in that House as if it were not a hybrid instrument. (4B) An order made by the Welsh Ministers under subsection (1) (by virtue of paragraph 30 of Schedule 11 to the Government of Wales Act 2006) does not have effect until approved by a resolution of the National Assembly for Wales. (4C) An order made by the Scottish Ministers under subsection (1) (by virtue of section 53 of the Scotland Act 1998) is subject to the affirmative procedure (see Part 2 of the Interpretation and Legislative Reform (Scotland) Act 2010 (asp 10)).

Propose a change

167 Establishment of urban development corporations: procedure

(1) Section 135 of the Local Government, Planning and Land Act 1980 (urban development corporations) is amended as follows. (2) After subsection (1) insert— (1A) Before making an order under this section in relation to an urban development area in England, the Secretary of State must consult the following persons— (a) persons who appear to the Secretary of State to represent those living within, or in the vicinity of, the urban development area; (b) persons who appear to the Secretary of State to represent businesses with any premises within, or in the vicinity of, the urban development area; (c) each local authority for an area which falls wholly or partly within the urban development area; and (d) any other person whom the Secretary of State considers it appropriate to consult. (3) For subsection (3) substitute— (3) A statutory instrument containing an order made by the Secretary of State under this section does not have effect until approved by a resolution of each House of Parliament. (3A) If a draft of an instrument containing an order by the Secretary of State under this section would, but for this subsection, be treated for the purposes of the standing orders of either House of Parliament as a hybrid instrument, it is to proceed in that House as if it were not a hybrid instrument. (3B) An order made by the Welsh Ministers under this section (by virtue of paragraph 30 of Schedule 11 to the Government of Wales Act 2006) does not have effect until approved by a resolution of the National Assembly for Wales. (3C) An order made by the Scottish Ministers under this section (by virtue of section 53 of the Scotland Act 1998) is subject to the affirmative procedure (see Part 2 of the Interpretation and Legislative Reform (Scotland) Act 2010 (asp 10)).

Propose a change

168 Sections 166 and 167: consequential repeals

In the Deregulation Act 2015, omit sections 46 and 47.

Propose a change

169 Designation of new town areas and establishment of corporations: procedure

(1) The New Towns Act 1981 is amended as follows. (2) In section 1 (designation of areas)— (a) after subsection (3) insert— (3A) Before making an order under this section designating an area of land in England as the site of a proposed new town, the Secretary of State must consult the following persons (as well as the local authorities mentioned in subsection (1))— (a) persons who appear to the Secretary of State to represent those living within, or in the vicinity of, the site; (b) persons who appear to the Secretary of State to represent businesses with any premises within, or in the vicinity of, the site; (c) any other person whom the Secretary of State considers it appropriate to consult. (b) in subsection (4), after “section” insert “ designating areas of land in Wales ”. (3) In section 3 (establishment of development corporations for new towns), after subsection (2) insert— (2A) Before making an order under this section in relation to a site in England, the Secretary of State must consult the following persons— (a) persons who appear to the Secretary of State to represent those living within, or in the vicinity of, the site; (b) persons who appear to the Secretary of State to represent businesses with any premises within, or in the vicinity of, the site; (c) every county or district council for an area which falls wholly or partly within the site; (d) any other person whom the Secretary of State considers it appropriate to consult. (4) In section 77 (regulations and orders)— (a) after subsection (3) insert— (3ZA) The power of the Secretary of State to make orders under section 3 is also exercisable by statutory instrument. ; (b) after subsection (3A) insert— (3B) A statutory instrument containing an order made by the Secretary of State under section 1, 2 or 3 may not be made unless a draft of the instrument has been laid before and approved by a resolution of each House of Parliament. (3C) If a draft of an instrument containing an order of the Secretary of State under section 1, 2 or 3 would, but for this subsection, be treated for the purposes of the standing orders of either House of Parliament as a hybrid instrument, it is to proceed in that House as if it were not a hybrid instrument. ; (c) in subsection (4), for the words before paragraph (a) substitute “ A statutory instrument that is made by the Welsh Ministers (by virtue of paragraph 30 of Schedule 11 to the Government of Wales Act 2006) under any of the following provisions of this Act is subject to annulment in pursuance of a resolution of the National Assembly for Wales— ”; (d) in subsection 4(a)(ii), omit “a county planning authority or, where the order is one designating an area in Wales, by”. (5) In Schedule 1 (procedure for designating area), before paragraph 1 (and before the italic heading before that paragraph) insert— Application of Schedule: Wales only A1 This Schedule applies only in relation to an order under section 1 designating an area of land in Wales as the site of a proposed new town.

Propose a change

170 New towns: objects of development corporations in England

In section 4 of the New Towns Act 1981 (objects and general powers of development corporations), after subsection (1) insert— (1A) In pursuing those objects a development corporation that is established for the purposes of a new town in England must aim to contribute to the achievement of sustainable development. (1B) For the purposes of subsection (1A) a development corporation must (in particular) have regard to the desirability of good design.

Propose a change

171 Sustainable drainage

The Secretary of State must carry out a review of planning legislation, government planning policy and local planning policies concerning sustainable drainage in relation to the development of land in England.

Propose a change

172 Right to enter and survey land

(1) A person authorised in writing by an acquiring authority may enter and survey or value land in connection with a proposal to acquire an interest in or a right over land. (2) The person— (a) may only enter and survey or value land at a reasonable time, and (b) may not use force unless a justice of the peace has issued a warrant under section 173(1) authorising the person to do so. (3) The person must, if required when exercising or seeking to exercise the power conferred by subsection (1), produce— (a) evidence of the authorisation, and (b) a copy of any warrant issued under section 173(1). (4) An authorisation under subsection (1) may relate to the land which is the subject of the proposal or to other land. (5) If the land is unoccupied or the occupier is absent from the land when the person enters it, the person must leave it as secure against trespassers as when the person entered it. (6) In this section and sections 173 to 178 — (a) “acquiring authority” means a person who could be authorised to acquire compulsorily the land to which the proposal mentioned in subsection (1) relates (regardless of whether the proposal is to acquire an interest in or a right over the land or to take temporary possession of it), and (b) “owner” has the meaning given in section 7 of the Acquisition of Land Act 1981.

Propose a change

173 Warrant authorising use of force to enter and survey land

(1) A justice of the peace may issue a warrant authorising a person to use force in the exercise of the power conferred by section 172(1) if satisfied— (a) that another person has prevented or is likely to prevent the exercise of that power, and (b) that it is reasonable to use force in the exercise of that power. (2) The force that may be authorised by a warrant is limited to that which is reasonably necessary. (3) A warrant authorising the person to use force must specify the number of occasions on which the authority can rely on the warrant when entering and surveying or valuing land. (4) The number specified must be the number which the justice of the peace considers appropriate to achieve the purpose for which the entry and survey or valuation are required. (5) Any evidence in proceedings for a warrant under this section must be given on oath.

Propose a change

174 Notice of survey and copy of warrant

(1) The acquiring authority must give every owner or occupier of land at least 14 days' notice before the first day on which the authority intends to enter the land in exercise of the power conferred by section 172. (2) Notice given in accordance with subsection (1) must include— (a) a statement of the recipient's rights under section 176, and (b) a copy of the warrant, if there is one. (3) If the authority proposes to do any of the following, the notice must include details of what is proposed— (a) searching, boring or excavating; (b) leaving apparatus on the land; (c) taking samples; (d) an aerial survey; (e) carrying out any other activities that may be required to facilitate compliance with the instruments mentioned in subsection (5). (4) If the authority obtains a warrant after giving notice in accordance with subsection (1) it must give a copy of the warrant to all those to whom it gave that notice. (5) The instruments referred to in subsection (3)(e) are— (a) Council Directive 85/337/EEC of 27 June 1985 on the assessment of the effects of certain public and private projects on the environment, as amended from time to time, (b) Council Directive 92/43/EC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora, as amended from time to time, or (c) any EU instrument from time to time replacing all or part of those Directives.

Propose a change

175 Enhanced authorisation procedures etc. for certain surveys

(1) A written authorisation from the appropriate Minister is required before a person enters and surveys or values land in exercise of the power conferred by section 172 if— (a) the land is held by a statutory undertaker, (b) within the notice period mentioned in section 174(1), the statutory undertaker objects to the proposed entry and survey or valuation in writing to the acquiring authority, and (c) the objection is that the proposed entry and survey or valuation would be seriously detrimental to the statutory undertaker carrying on its undertaking. (2) In subsection (1)— “the appropriate Minister” means— in the case of land in Wales held by a water or sewerage undertaker, the Welsh Ministers, and in any other case, the Secretary of State; “statutory undertaker” means— any person who is, or who is deemed to be, a statutory undertaker for the purposes of section 16 or 17 of the Acquisition of Land Act 1981 or of any provision of Part 11 of the Town and Country Planning Act 1990, and any person in relation to whom the electronic communications code is applied by a direction under section 106(3)(a) of the Communications Act 2003. (3) Where the survey or valuation is to take place in a street, the following sections of the New Roads and Street Works Act 1991 apply to the survey or valuation as if it were street works— (a) section 55 (notice of starting date of works), (b) section 69 (requirements to be complied with where works likely to affect another person's apparatus in the street), and (c) section 82 (liability for damage or loss caused). (4) In the application of those sections references to an “undertaker” are to be read as references to the acquiring authority which authorised the survey or valuation. (5) See section 169(4) of the Water Industry Act 1991 and section 171(4) of the Water Resources Act 1991 for additional procedures in relation to the exercise of the power in section 172 on behalf of a water undertaker, the Environment Agency or the Natural Resources Body for Wales.

Propose a change

176 Right to compensation after entry on or survey of land

(1) A person interested in land is entitled to compensation from the acquiring authority for damage as a result of the exercise of the power conferred by section 172. (2) Any disputes relating to compensation under this section are to be determined by the Upper Tribunal. (3) The provisions of section 4 of the Land Compensation Act 1961 apply to the determination of such disputes, with any necessary modifications.

Propose a change

177 Offences in connection with powers to enter land

(1) A person who without reasonable excuse obstructs another person in the exercise of the power conferred by section 172 commits an offence. (2) A person who commits an offence under subsection (1) is liable on summary conviction to a fine not exceeding level 3 on the standard scale. (3) A person commits an offence if the person discloses confidential information, obtained in the exercise of the power conferred by section 172, for purposes other than those for which the power was exercised. (4) A person who commits an offence under subsection (3) is liable— (a) on summary conviction to a fine, (b) on conviction on indictment to imprisonment for a term not exceeding 2 years or to a fine, or both. (5) In subsection (3) “confidential information” means information— (a) which constitutes a trade secret, or (b) the disclosure of which would or would be likely to prejudice the commercial interests of any person.

Propose a change

178 Right to enter and survey or value Crown land

(1) Sections 172 to 177 apply in relation to Crown land. (2) But a person may only exercise the power conferred by section 172 in relation to Crown land if the person has the permission of the appropriate authority. (3) In this section, “Crown land” and “the appropriate authority” have the meaning given in section 293 of the Town and Country Planning Act 1990.

Propose a change

179 Amendments to do with sections 172 to 178

Schedule 14 amends legislation conferring rights of entry relating to the acquisition of an interest in or a right over land in England and Wales.

Propose a change

180 Timetable for confirmation of compulsory purchase order

After section 14A of the Acquisition of Land Act 1981 (confirmation by acquiring authorities) insert— Timetables for confirmation of CPOs except by Welsh Ministers 14B (1) The Secretary of State must publish one or more timetables in relation to steps to be taken by confirming authorities, other than the Welsh Ministers, in confirming a compulsory purchase order. (2) Different timetables may be published in relation to— (a) different confirming authorities, or (b) different types of compulsory purchase order. (3) The Secretary of State may at any time revise a timetable published under this section. (4) The validity of an order is not affected by any failure to comply with a timetable published under this section. (5) The Secretary of State must lay before Parliament an annual report showing the extent to which confirming authorities have complied with any applicable timetable published under this section. (6) A report laid by the Secretary of State under this section need not include information about a confirming authority if the number of compulsory purchase orders submitted to it is lower than a minimum specified by the Secretary of State in the report. Timetables for confirmation of CPOs by Welsh Ministers 14C (1) The Welsh Ministers may publish one or more timetables in relation to steps to be taken by them in confirming a compulsory purchase order. (2) Different timetables may be published in relation to different types of compulsory purchase order. (3) The Welsh Ministers may at any time revise a timetable published under this section. (4) The validity of an order is not affected by any failure to comply with a timetable published under this section. (5) The Welsh Ministers must lay before the National Assembly for Wales an annual report showing the extent to which they have complied with any applicable timetable published under this section.

Propose a change

181 Confirmation by inspector

(1) The Acquisition of Land Act 1981 is amended as follows. (2) After section 14C (inserted by section 180 of this Act), insert— Power to appoint inspector 14D (1) A confirming authority may appoint a person (“an inspector”) to act instead of it in relation to the confirmation of a compulsory purchase order to which section 13A applies. (2) An inspector may be appointed to act in relation to— (a) a specific compulsory purchase order, or (b) a description of compulsory purchase orders. (3) An inspector— (a) has the same functions as a confirming authority under this Part (excluding this section), (b) retains those functions even if all remaining objections are withdrawn after the inspector has begun to act in relation to a compulsory purchase order, and (c) may hold a public local inquiry under section 13A(3)(a) or act as the person appointed to hear remaining objections under section 13A(3)(b). (4) Where an inspector is to act in relation to a compulsory purchase order, the confirming authority must inform— (a) every person who has made a remaining objection, and (b) the acquiring authority. (5) Where an inspector decides whether or not to confirm the whole or part of a compulsory purchase order, the inspector's decision is to be treated as that of the confirming authority. (6) The confirming authority may at any time— (a) revoke its appointment of an inspector, and (b) appoint another inspector. (7) If the confirming authority revokes its appointment of an inspector while the inspector is acting in relation to a compulsory purchase order and does not replace the inspector, the authority must give its reasons— (a) to the inspector whose appointment has been revoked, and (b) to all those informed under subsection (4). (8) Where in any enactment there is a provision that applies in relation to a confirming authority acting under this Part, that provision is to be read as applying equally in relation to an inspector so far as the context permits. (9) In this section “remaining objection” is to be construed in accordance with section 13A. (3) In section 2 (procedure for authorisation), for subsection (2) substitute— (2) A compulsory purchase order authorising a compulsory purchase by an authority other than a Minister is to be— (a) made by that authority, (b) submitted to the confirming authority, and (c) confirmed in accordance with Part 2 of this Act.

Propose a change

182 Time limits for notice to treat or general vesting declaration

(1) For section 4 of the Compulsory Purchase Act 1965 substitute— Time limit for giving notice to treat 4 A notice to treat may not be served by the acquiring authority after the end of the period of 3 years beginning with the day on which the compulsory purchase order becomes operative. (2) After section 5 of the Compulsory Purchase (Vesting Declarations) Act 1981 insert— Time limit for general vesting declaration 5A A general vesting declaration may not be executed after the end of the period of 3 years beginning with the day on which the compulsory purchase order becomes operative.

Propose a change

← Find another law