Law

The Hornsea Four Offshore Wind Farm (Amendment) Order 2024

United Kingdom · regulation

Ask the law about thisMore laws of United KingdomFor machines: Markdown

Open at the publisher →

In force since 2024-07-18, as the publisher states.

Copy read on 2026-11-10. The page it was read from

Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

sha256 6f6354d2cb52d34dd80fb2b8a7fb124c69a168269c16052e2b3b4a91cbdf1db0

Contents: 4 provisions
  1. Title and introductory text
  2. 1 Citation and commencement
  3. 2 Amendment to the Hornsea Four Offshore Wind Farm Order 2023
  4. 3 Amendments to Schedule 16 of the 2023 Order

Proposed changes to this act

No one has proposed a change to this act yet.

How this law is officially changed

Solon does not know this law's official route yet. The proposal is recorded all the same, and the route appears here once its source is added.

4 provisions

Title and introductory text

2024 No. 800 Infrastructure Planning The Hornsea Four Offshore Wind Farm (Amendment) Order 2024 Made 17th July 2024 Coming into force 18th July 2024 An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for non-material changes to the Hornsea Four Offshore Wind Farm Order 2023. The Secretary of State, having considered the application, the responses to the publicity and consultation required by Regulations 6 and 7 of the 2011 Regulations, has decided to make the changes on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application. Accordingly, the Secretary of State, in exercise of the powers conferred by paragraphs 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order—

Propose a change

1 Citation and commencement

This Order may be cited as the Hornsea Four Offshore Wind Farm (Amendment) Order 2024 and comes into force on 18th July 2024.

Propose a change

2 Amendment to the Hornsea Four Offshore Wind Farm Order 2023

The Hornsea Four Offshore Wind Farm Order 2023 (“the 2023 Order”) is amended in accordance with this Order.

Propose a change

3 Amendments to Schedule 16 of the 2023 Order

In Part 2 of Schedule 16 to the 2023 Order— (a) in paragraph 3(d) for “four full kittiwake breeding seasons” substitute “two full kittiwake breeding seasons”; and (b) in paragraph 4, for “four full breeding seasons” substitute “two full breeding seasons”.